Legislation Details

File #: 24-0666    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 1/23/2024 In control: Commissioners Court
On agenda: 1/30/2024 Final action: 1/30/2024
Title: Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills for 9155 1/2 Queenston Boulevard, Houston, TX 77095 (Detention Basin Enhancement Program - Goforth - 2021) for electrical power serving a pump station, UPIN 21103N306330001, Precinct 3.
Attachments: 1. 24-0666-SOLS-UPIN-21103N306330001-2023-12-14 Goforth -91555 Half Queenstone Blvd- PCT 3-RCA-01 30 2024

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

 

Project ID (if applicable): 21103N306330001

 

Vendor/Entity Legal Name (if applicable): CenterPoint Energy, LLC

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to execute a Service Outlet Location Statement for installation of an electric meter with CenterPoint Energy, LLC and authorize the County Auditor to pay monthly bills for 9155 ½ Queenston Boulevard, Houston, TX 77095 (Detention Basin Enhancement Program - Goforth - 2021) for electrical power serving a pump station, UPIN 21103N306330001, Precinct 3.

end

 

Background and Discussion:

Detention Basin Enhancement Program - Goforth - 2021 is a project to maximize the detention volume prior to a significant rainfall event by reducing the initial water surface elevation. The service outlet location statement is needed to establish electrical service from CenterPoint Energy to power the pump station.

 

Expected Impact:

Approval of the service outlet location statement will allow CenterPoint Energy to establish electrical service to the pump station, which is needed to enhance the detention basin at this location.

 

Alternative Options:

All pump stations require a power source, which is typically obtained through CenterPoint Energy. A less desirable option would be to use a generator.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_Transportation

X Flooding

_ Environment

_ Governance and Customer Service

Prior Court Action (if any): List all instances of prior Commissioners Court action that relates to this item (Original Project Award).

 

Date

Agenda Item #

Action Taken

7/18/2023

55

Centerpoint Facilities Extension Agreement

 

 

 

 

Location:

Address (if applicable): 9155 ½ Queenston Blvd, Cypress, Texas 77095

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 30, 2024

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Dr. Hatem Elbastawisy, PE - (Interim) Senior Director of Project Delivery - Harris County Engineering Department

Attachments (if applicable):  SOLS