Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer
Managing Department: County Engineer
Managing Department Head/Elected Official: Milton Rahman, PhD., P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo
Project Name: Roofing Systems Repair and Replacement Countywide
Project ID (if applicable): MF0ROOFS
Vendor Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Incremental Authorization Requested: $4,588,152
Total Estimated Project Cost: $24,915,000 (FY26-30)
Request Summary:
title
Request for approval of a Final Investment Memo for the Roofing Systems Repair and Replacement Countywide projects for an incremental authorization of $4,588,152 for a total FY2026 authorization of $4,983,152, and a request for Commercial Paper funding for an additional amount of $2,840,000.
end
Project Description:
This is a continuous lifecycle management project to identify and construct all required Roofing System upgrades and improvements for County facilities that are currently maintained by Building Operations Services (BOS).
Below are the planned allocations; there might be changes in the County’s needs that result in minor operational changes for the projects throughout the Fiscal Year, but overall scope will remain the same, and any additional authorization would go through Commissioners Court approval.
Anticipated Project Expenditures and Timeline:
|
Project Scope Breakdown |
Estimated Cost |
Estimated Completion |
|
Evelyn Meador Library - 2400 N. Meyer Ave. |
$325K |
FY2026 |
|
Freeman Memorial Library -16602 Diana Lane |
$637K |
FY2027 |
|
Octavia Fields Library - 1503 S. Houston Ave |
$400K |
FY2026 |
|
Annex 73 - Civil Courthouse - 201 Caroline St |
$838K |
FY2027 |
|
Annex 73 - Civil Courthouse - 201 Caroline St |
$450K |
FY2027 |
|
Atascocita Branch Library - 19520 Pinehurst Trails Dr |
$430K |
FY2026 |
|
Parker Williams Branch Library - 10851 Scarsdale Blvd |
$470K |
FY2026 |
|
Annex 67 - Scarsdale Annex - 10851 Scarsdale Blvd |
$480K |
FY2027 |
|
Hooks Airport, 20803 Stuebner Airline Rd |
$500K |
FY2026 |
|
FY 2026 Total Authorization |
$4,530K |
|
|
Contingency 10% |
$453K |
|
|
FY 2026 Total Authorization |
$4,983K |
|
|
FY 2025 Carry Forward |
$(395)K |
|
|
Total |
$4,588K |
|
Justification & Alternatives:
The Office of the County Engineer (OCE) continues to experience the effects of previous years’ inflation regarding materials and labor for construction projects. Although inflation for costs of materials and labor is expected to increase at historical averages in FY2026, the increases from previous years are expected to remain.
Not funding this program would lead to an even greater backlog of deferred maintenance to perform later and, in some cases, could create hazards to life and safety. Delay in project timeline may increase costs due to increased deterioration of infrastructure, potential bid increases, and increase in material and labor costs.
Anticipated Impact on Other Funds (If Applicable):
|
Fund Code |
Description |
Estimated Cost |
Funding Method (Existing or Future Budget Request Required) |
Estimated Date of Needs |
|
|
|
$- |
|
- |
|
|
|
$- |
|
- |
|
Total |
|
$- |
|
- |
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): T2: Make County buildings more energy efficient.
Housing Initiative (Goal 6): N/A
Previous Court Action:
|
Date |
Agenda Item # |
Action Taken |
|
8/1/2017 |
4.d.5 |
$5M CP allocation |
|
3/27/2018 |
1.t.2 |
$2M authorization |
|
4/10/2018 |
4.e.1 |
$2M CP allocation |
|
8/28/2018 |
1.o.1 |
$2M authorization |
|
9/11/2018 |
3.f.7 |
$2M CP allocation |
|
6/4/2019 |
1.u.5 |
$3M authorization per Interim CIP |
|
7/9/2019 |
3.f.4 |
$2M CP allocation |
|
8/27/2019 |
4.e.1 |
$1M CP allocation |
|
1/7/2020 |
II.1.d |
$5M authorization per FY20 CIP |
|
6/30/2020 |
1.s.2 |
$5M authorization |
|
7/14/2020 |
4.h.2 |
$5M CP allocation |
|
3/9/2021 |
88 |
Harris County - Proposed Capital Improvements Program; Facility and Maintenance Projects: Roofing Systems Repair and Replacement Countywide, pages 281 and 292 ($1.94M authorization for FY21-22) |
|
8/24/2021 |
94 |
$3,516,480 incremental authorization for FY21-22; $3.295M CP allocation |
|
3/8/2022 |
113 |
$3,516,480 incremental authorization for FY21-22; $3.295M CP allocation |
|
10/18/2022 |
128 |
Request for approval of a Final Investment Memo for the Roofing Systems Repair and Replacement Countywide project for an additional $3,166,000 fora FY 2023 authorization of $7,327,000. 22-6666 |
|
12/13/2022 |
22.22 |
Request for approval of commercial paper funding for the Office of the County Engineer for the Roofing Systems Repair and Replacement Countywide project in the additional amount of $500,000 for a total CP funding of $29,125,000 |
|
2/21/2023 |
23.03 |
Request for approval of commercial paper funding for the Office of the County Engineer for the Roofing Systems Repair and Replacement Countywide project in the additional amount of $1,470,000 for a total CP funding of $30,595,000. |
|
4/25/2023 |
23.06 |
Request for approval of commercial paper funding for the Office of the County Engineer for the Roofing Systems Repair and Replacement Countywide project in the additional amount of $1,200,000 for a total CP funding of $31,795,000. |
|
8/29/2023 |
23.15 |
Request for approval of a Final Investment Memo for the Roofing Systems Repair and Replacement Countywide project for an additional $1,945,000 for a FY24 authorization of $3,832,000. |
|
10/31/2023 |
23.19 |
Request for approval of commercial paper funding for the Office of the County Engineer for the Roofing Systems Repair and Replacement Countywide project in the additional amount of $1,000,000 for a total CP funding of $31,595,000. |
|
11/14/2023 |
23.20 |
Request for approval of commercial paper funding for the Office of the County Engineer for the Roofing Systems Repair and Replacement Countywide project in the additional amount of $945,000 for a total CP funding of $32,540,000. |
|
8/6/2024 |
84 |
Request for approval of a Final Investment Memo for the Roofing Systems Repair and Replacement Countywide project for a FY2025 authorization of $6,635,000 and request for commercial paper funding for an amount of $ 1,030,000. |
|
05/08/2025 |
30 |
Request for approval of commercial paper funding for Office of the County Engineer for the Roofing Systems Repair and Replacement Countywide project in the additional amount of $ 1,255,000 for a total CP funding of $36,025,000. |
Address: Countywide
Precinct(s): Countywide
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
|
|
|
|
|
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request |
|
|
Commercial Paper |
$ |
$2,840,000 |
$2,840,000 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$2,840,000 |
$2,840,000 |
$ |
|
Total Funding Request |
$ |
$2,840,000 |
$2,840,000 |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 1/29/2026
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item
Legal funding compliance confirmed by: Paige Abernathy, Special Assistant County Attorney, 1/21/2026
Department Approval by: Samuel Peña, Chief of Infrastructure Services and Disaster Recovery
Office of County Engineer
OMB CIP Team Approval by: Wanwei Tang, Analyst - Capital Projects and Infrastructure, 1/20/2026

Commercial Paper Request (For OMB use only):
Receiving Department: County Engineer
Project PeopleSoft ID: MF0ROOFS
CP Series Description: Commercial Paper Series D can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).
Commercial Paper is being requested for the Roof repair and Replacement project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.
Note: Commercial Paper is issued in increments of $5,000 and the excess is not available to be spent by the department.
OMB Financial Management contact: Fahad Gulzar, Acting Deputy Executive Director, Office of Management and Budget