Legislation Details

File #: 24-3109    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/20/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a change in contract with WadeCon, LLC, in connection with Beaumont Place Subdivision Drainage Improvements - 2018, adding 26 calendar days, Job No. 22/0199-6, UPIN 19101MF17901, Precinct 2, MWDBE Contracted Goal: 21%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 22/0199 - UPIN 19101MF17901

Vendor/Entity Legal Name (if applicable): WadeCon, LLC

 

MWDBE Contracted Goal (if applicable): 21%

MWDBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with WadeCon, LLC, in connection with Beaumont Place Subdivision Drainage Improvements - 2018, adding 26 calendar days, Job No. 22/0199-6, UPIN 19101MF17901, Precinct 2, MWDBE Contracted Goal: 21%.

end

 

Background and Discussion:

This project is located in the Greens Bayou watershed near Highway 90 and Beltway 8. The Beaumont Place subdivision consists of mainly roadside ditches and has been subjected to several flooding events with the most recent being Hurricane Harvey (August 2017) and the Tax Day Flood (April 2016). Drainage analysis of the subdivision began in late 2019 as a part of the 2018 Bond program for subdivision drainage improvements. The scope and proposed improvements include roadside ditch regrading, driveway culvert upgrades, expansion of channel along Big Gulch, concrete lined Sulphur Gully channel with reinforced concrete box (RCB) crossing improvements. Improvements also include multiple detention ponds along Big Gulch with an extreme event overflow swale towards the upstream portion of the channel.

 

The Change in contract request includes the following:

 

•                     PCO - 8 Driveway Variations - Added 26 days for an extension of contract time due to the replacement of existing driveways with culverts not shown on the design plans. A total of 13 existing driveways with culverts along Columbine, Elderberry, and Edgehill were not shown on the design plans, but will be replaced as part of the drainage improvements.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This change in contract is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the

financial impact of recovery costs to the Beaumont Place Subdivision homeowners, Harris County, and FEMA. The fiscal impact for this project will come from the 1080 Funding for the Recovery and Resiliency Division subdivision projects with the long-term goal of reducing drainage costs in the future.

 

Alternative Options:

The County could elect to approve the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete scope of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/02/2022

220

Contract Award

05/16/2023

51

Change Order Approved

09/19/2023

44

Change Order Approved

10/31/2023

36

Change Order Approved

10/31/2023

38

Change Order Approved

03/26/2024

88

Change Order Approved

 

Location: Beaumont Place Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: June 04, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Change in Contract (CIC)