Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Termination
Project ID (if applicable): UPIN 22103N301030006
Vendor/Entity Legal Name (if applicable): Cobb, Fendley & Associates, Inc.
MWDBE Contracted Goal (if applicable):
MWDBE Current Participation (if applicable):
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a Mutual Termination Agreement with Cobb, Fendley & Associates, Inc. in connection with Peek Road Segment 3 - from north of Stockdick School Road to north of Beckendorff Road - 2021, UPIN 22103N301030006, Precinct 4 (Previously Precinct 3).
end
Background and Discussion:
The professional services contract was originally executed on 9/14/2021 with Cobb, Fendley & Associates, Inc. in the amount of $1,099,650.30. No amendments were made to the contract. This project has been mutually agreed upon for termination. An amount of $450,711.03 in unexpended funds will be returned to the County as part of the termination of the agreement.
Expected Impact:
Termination of the agreement and return of the remaining funds.
Alternative Options:
No alternative option. Both parties agree to mutually terminate the agreement.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
9/14/2021 |
35. |
Request for approval of an agreement with Cobb Fendley & Associates, Inc. in the amount of $1,099,650.30 for Professional Engineering Services for improvements to Peek Road Segment 3 from north of Stockdick School Road to north of Beckendorff Road, UPIN 22103N301030006, Precinct 3. |
5/16/2023 |
72. |
Request for approval to execute a Joint Participation Interlocal Agreement with Harris County Municipal Utility District No. 540 to update their Master Drainage Plan to accommodate detention needs for the Peek Road Segment 3 project, UPIN 22103N301030006, Precinct 4. |
Location:
Address (if applicable): Peek Road- from North of Stockdick School Road to North of Beckendorff Road
Precinct(s): Precinct 4
Fiscal and Personnel Summary |
Service Name |
Professional Engineering Services |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: February 27, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Hatem Bastawisy, PE, (Interim) Senior Director of Project Delivery, Harris County Engineering Department
Attachments (if applicable): Professional Services Agreement