Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Brookstone LP, in connection with the Harris County Precinct One Administration Office and Service Center, Job No. 21/0309, UPIN 20101MF1ET01, Precinct 1, MWBE Contracted Goal: 17%, MWBE Current Participation: 29.63%.
Sponsors: Mony Hossain
Attachments: 1. 25-0090-SC-UPIN 20101MF1ET01 Pct 1 - Brookstone - P1-1.09

Primary Department: County Engineer

Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official:

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

 

Project ID (if applicable): 21/0309

Vendor/Entity Legal Name (if applicable):

 

MWBE Contracted Goal (if applicable): 17%

MWBE Current Participation (if applicable):29.63%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Transmittal by the Office of the County Engineer of a substantial completion certificate with Brookstone LP, in connection with the Harris County Precinct One Administration Office and Service Center, Job No. 21/0309, UPIN 20101MF1ET01, Precinct 1, MWBE Contracted Goal: 17%, MWBE Current Participation: 29.63%.

end

 

Background and Discussion:

 

The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets and Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.

 

Completion Date for this project is established to be November 26, 2024.

 

Expected Impact:

 

 This action establishes the date on which a capital improvement enters service as a Harris County asset.

 

 

 

 

Alternative Options:

N/A.

 

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/9/2021

239

Approved - Project Advertisement - Transmittal by the Office of the Purchasing Agent of a project scheduled for advertisement for construction of a new Administration Office and Service Center in Precinct 1 for the Office of the County Engineer (210309).

2/22/2022

243

Approved - Contract Award - Request for approval of an award on the basis of best proposal meeting requirements to Brookstone, LP in the amount of $21,700,000 for construction of a new Administration Office and Service Center in Precinct 1, subject to applicable bonds to be received (210309).

8/8/2023

41

Approved - Change in Contract# 21/0309-1 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $583,758.00, Job No. 21/0309-1, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal 17%.

9/19/2023

55

Approved - Change in Contract# 21/0309-2 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $49,267.00, Job No. 21/0309-2, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal 17%.

10/10/2023

56

Approved - Change in Contract# 21/0309-3 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding an additional amount of $18,085.00, Job No. 21/0309-3, UPIN 20101MF1ET01, Precinct 1.

11/14/2023

40

Approved - Change in Contract# 21/0309-4 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $35,726.00, Job No. 21/0309-4, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%

12/5/2023

43

Approved - Change in Contract# 21/0309-5 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $33,776.00, Job No. 21/0309-5, UPIN 20101MF1ET01, Precinct 1.

12/19/2023

44

Approved - Change in Contract# 21/0309-6 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 163 calendar days, with an addition in the amount of $382,123.00, Job No. 21/0309-6, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 17%.

12/30/2023

77

Approved - Change in Contract# 21/0309-7 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $89,972.00, Job No. 21/0309-7, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%

3/26/2024

54

Approved - Change in Contract# 21/0309-8 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 123 calendar days, with an addition in the amount of $323,326.00, Job No. 21/0309-8, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%

5/7/2024

58

Approved - Change in Contract# 21/0309-9 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $24,042.00, Job No. 21/0309-9, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

5/7/2024

45

Approved - Change in Contract# 21/0309-10 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 118 calendar days, with an addition in the amount of $917,863.00, Job No. 21/0309-10, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

6/4/2024

74

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $69,658.00, Job No. 21/0309-11, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%. MWDBE Current Participation: 32%.

6/25/2024

54

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $32,613.00, Job No. 21/0309-12, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

8/6/2024

49

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 74 calendar days, with an addition in the amount of $264,033.00, Job No. 21/0309-13, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

8/27/2024

61

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $102,075.00, Job No. 21/0309-14, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

9/19/2024

48

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $60,329.00, Job No. 21/0309-15, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

11/12/2024

71

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $38,003.00, Job No. 21/0309-16, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

 

Location:

Address (if applicable): 2787 El Camino Street, Houston, TX 77054

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/9/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Truitt Rounsavall, PE, MBA, PMP, LSSBB, Assistant Director of Capital Project Facilities, Engineering Group

 

 

Attachments (if applicable): AIA Document G704 - Certificate of Substantial Completion