File #: 24-5827    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 9/6/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval of a Final Investment Memo for the Annex Facilities Security Upgrades Countywide project (continuous) for an incremental authorization of $4,574,000 for a total FY2025 authorization of $5,074,000.
Sponsors: Mony Hossain

Department: County Engineer

Department Head: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Annex Facilities Security Upgrades Countywide

Project ID (if applicable): MF0ZM

Vendor Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Managing Entity: County Engineer

Incremental Authorization Requested: $4,574,000

Total Estimated Project Cost: $27,000,000 (FY25-29)

 

Request Summary:

title

Request for approval of a Final Investment Memo for the Annex Facilities Security Upgrades Countywide project (continuous) for an incremental authorization of $4,574,000 for a total FY2025 authorization of $5,074,000.

end

 

Project Description:

This is a continuous lifecycle management project to implement security upgrades at Annex facilities throughout the County. These upgrades might include the installation of cameras, card readers, or alarm systems.  This project may also install panic buttons and bullet-resistant barriers. These Annex security upgrades are intended to provide enhanced facility security, as well as identify and address all required repairs and/or replacements of existing security systems in County facilities that are currently being maintained by HCED - Building Operations Services.

 

Project Scope:

Annex Facilities Security Upgrades is a Countywide Program within HCED’s Capital Improvement Plan for asset/equipment replacement and major upgrade projects. This year HCED continues to perform security upgrades to include ballistic material, Countywide fencing installations, downtown security camera system replacement/upgrades, countywide card reader installation to include high-security Trilogy lock replacements, replacement/upgrading high-security/high-wear locks, gate controllers, and intercom systems at correctional facilities, courthouses, and multiuse facilities.

There might be changes in the County’s needs that result in minor operational changes for the project throughout the Fiscal Year, but the overall scope will remain the same, and any additional authorization would go through Commissioners Court approval.

 

Justification:

Security is critical to both the safety and peace of mind of County employees and visitors to County facilities. Security systems must be regularly maintained and upgraded to meet the ever-changing advancements in technology. These enhancements may also be necessary to meet code requirements. The main technological components of facility security systems are cameras and card readers. These tools document who enters and leaves the facility. This has practical administrative uses but is also useful in an emergency to quickly identify who may or may not be in the building. These enhanced security system components can represent cost savings by reducing the number of on-site personnel needed to secure a facility. Visible security cameras are a proven deterrent to costly vandalism and theft.  Facility security also includes protective materials and features.  These protect people within the facility by providing a physical barrier between occupants and dangers.

HCED continues to experience the effects of previous years’ inflation regarding materials and labor for construction projects.  Although inflation for costs of materials and labor is expected to increase at historical averages in FY2025, the increases from previous years are expected to remain.

 

Alternatives and Engagement:

Not funding this program would lead to an even greater backlog of deferred maintenance to perform later and, in some cases, could create hazards to life and safety. Delay in project timeline may increase costs due to increased deterioration of infrastructure, potential bid increases, and increase in material and labor costs.

 

Anticipated Project Expenditures and Timeline:

Scope of Work

FY25 Projected Estimates

Estimated Completion

Downtown Building Security Camera System

$778K

FY25

1111 Fannin - Security Upgrade

$133K

FY25

Annex 10 - Bay Area Annex - 16603 Buccaneer Ln, JP 8-2 Ballistic material installation (rollover project)

$500K

FY25

Annex 17 - Cypresswood Courthouse - 6831 Cypresswood Dr, JP 4-1 Ballistic material installation (rollover project)

 

Complete

Annex 2 - Fire Station - 1302 Preston, JP 1-2 Ballistic material installation (rollover project)

$800K

FY25

Annex 8 - Clinton F. Greenwood Courthouse - 701 W Baker Rd, JP 3-2 Ballistic material installation (rollover project)

 

Complete

Annex 53 - Administration Bldg., Constable Pct. 1 Ballistic security upgrades

 

Complete

Annex 38 - Antoine WIC Center - 5815 Antoine - New Fencing and Gate Project to secure new vulnerabilities found at this location

$230K

FY25

Annex 39 - Lockwood Annex - 333 Lockwood Dr. - Security upgrades to include Ballistic Materials and Renovations

$345K

FY25

Annex 84 - 1111 Fannin - 1111 Fannin - Security upgrades include access controls and cameras

 

Complete

330 Meadowfern - Security upgrades include access controls and cameras

$288K

FY25

Household Hazardous Waste (HHW) Collection Facility - 6900 Hahl Road - Modular Trailer relocation from Riverside 3204 Ennis to Region 4 HQ. Trailer disconnects, transport, reconnect. New fencing and access gates, new blacktop

 

Complete

Annex 31 - Mickey Leland Annex - 7300 N. Shepherd Dr., JP 1-1Security upgrades to include Ballistic Materials and Renovations

$500K

FY25

Annex 4 - John Phelps Courthouse - 101 S. Richey - Security upgrades to include Ballistic Materials and Renovations

$500K

FY25

Annex 14 - Southeast Annex - 5737 Cullen Blvd. - Security upgrades to include Ballistic Materials and Renovations

$500K

FY25

Youth Village - 210 J.W. Mills, Seabrook TX.  Security arm at the facility with a gate of remote control /badge access/ camera system

$500K

FY25

Total planned FY25 expenditures

$5,074K

 

Unencumbered existing project balance to carry into FY25

$(500K)

 

Total

$4,574K

 

Note: Certain work packages will be completed after the end of FY25, but purchase orders will need to be encumbered in FY25 to ensure on-time delivery & installation, and thus are included in the total incremental ask.  Final individual project cost increases from FY25 are due to the County efforts to improve security within workplace and correctional facilities and properties.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Previous Court Action:

Date

Agenda Item #

Action Taken

5/1/2018

1.q

$1.5M authorization

8/22/2018

4.g

$1.5M CP allocation

7/14/2020

1.n.1

$1M authorization in CIP

7/28/2020

1.i

$1M CP allocation

3/9/2021

88

Harris County - Proposed Capital Improvements Program; Facility and Maintenance Projects: Annex Facilities Security Upgrades Countywide, pages 281 and 282 ($1M authorization for FY21-22)

8/24/2021

94

$25K CP reduction

3/8/2022

104

Request for approval of a Final Investment Memo for the Annex Facilities Security Upgrades Countywide project for an additional $1,684,000 for a SFY 22 authorization of $1,900,000 for HCED and request for approval of commercial paper funding for Engineering for the project in the additional amount of $1,115,000 for a total of $3,825,000. (p.13).

12/13/2022

82

Request for approval of a Final Investment Memo for the Annex Facilities Security Upgrades Countywide project (continuous) for an additional incremental authorization of $4,172,000 for a total FY23 authorization of $5,910,000. 22-7751.

5/16/2023

23.07

Request for approval of commercial paper funding for the Office of the County Engineer for the Annex Facilities Security Upgrades Countywide project in the additional amount of $75,000 for a total CP funding of $3,900,000.

8/29/2023

23.15

Request for approval of a Final Investment Memo for the Annex Facilities Security Upgrades Countywide project (continuous) for an additional incremental authorization of $2,379,000 for a total FY24 authorization of $3,068,000.

6/4/2024

24.16

Request for approval of commercial paper funding for the Office of the County Engineer for the Annex Facilities Security Upgrades Countywide project in the additional amount of $1,700,000 for a total CP funding of $5,600,000

 

Address: Countywide

Precinct(s): Countywide

 

Fiscal and Personnel Summary

Service Name

Property Maintenance

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

0

-

0

0

Additional Positions Request

0

-

0

0

Total Personnel

0

-

0

0

 

Anticipated Court Date: 09/19/2024

Anticipated Implementation Date (if different from Court date):

Legal funding compliance confirmed by: Paige Abernathy, Assistant County Attorney, 7/19/2024

Department Approval by: Rosalie Brockman. Director - Building Resiliency & Sustainability Operations

OMB CIP Team Approval by: Wanwei Tang, Analyst - Capital Projects and Infrastructure, 8/12/24

 

Commercial Paper Request (For OMB use only):

Receiving Department: Choose an item.

Project PeopleSoft ID:

CP Series Description:

OMB Financial Management contact: