File #: 25-0097    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 12/23/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval to execute an agreement with IEA, Inc. for professional engineering services in the amount of $605,000.00 for the assessment and design of the SH 249 Tomball Tollway Pavement Surface Repairs design, bidding phase, and construction phase services (Precinct 3 & 4, MWBE Contracted Goal: 19.6%).
Attachments: 1. 25-0097 IEA_AGREEMENT_(SH_249_Tomball_Tollway).doc

Primary Department: Toll Road Authority

Primary Department Head/Elected Official: Roberto Treviño, P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): N/A

Vendor/Entity Legal Name (if applicable): IEA, Inc.

 

MWBE Contracted Goal (if applicable): 19.6%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with IEA, Inc. for professional engineering services in the amount of $605,000.00 for the assessment and design of the SH 249 Tomball Tollway Pavement Surface Repairs design, bidding phase, and construction phase services (Precinct 3 & 4, MWBE Contracted Goal: 19.6%).

end

 

Background and Discussion:

On August 6, 2024, Commissioners Court approved negotiations with IEA, Inc. for professional engineering services for the assessment and design of the SH 249 Tomball Tollway Pavement Surface Repairs design, bidding phase, and construction phase services. Pavement surface replacement of Tomball Tollway is due for maintenance in the section that was installed in 2015. The existing surface is an asphalt Permeable Friction Course (PFC) which currently has a 5-8 year life cycle. As part of the design phase, the designer will evaluate alternatives to PFC that are cost effective, require less maintenance, and longer life spans while providing the same or better level of driver safety.

 

Expected Impact:

Cost effective recommendations and improved roadway conditions.

 

Alternative Options:

No other recommended option for this identified need.

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

8/6/2024

152

Request to Negotiate

 

Location:

Address (if applicable): N/A

Precinct(s): Precincts 3 & 4

 

Fiscal and Personnel Summary

Service Name

Roadway & Facility Infrastructure Maintenance

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Revenue - TRA

$

$350,000

$350,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$350,000

$350,000

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$350,000

$350,000

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/9/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority

 

Attachments (if applicable): Agreement