Title: Request for approval to execute an agreement with Woolpert, Inc. in the amount of $352,481.40 for Construction Phase Services in connection with Ralston Acres Subdivision Drainage Improvements-2018, UPIN 19101MF16P01, Precinct 1.
Attachments: 1. 25-0355-Consultant-UPIN 19101MF16P01-Ralston Acres- Woolpert

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 19101MF16P01; Job No. 24/0368

Vendor/Entity Legal Name (if applicable): Woolpert, Inc.

 

MWBE Contracted Goal (if applicable): 0%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  0% - Non-Divisible

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Woolpert, Inc. in the amount of $352,481.40 for Construction Phase Services in connection with Ralston Acres Subdivision Drainage Improvements-2018, UPIN 19101MF16P01, Precinct 1.

end

 

Background and Discussion:

Ralston Acres is in northeast Harris County, Precinct 1.  The project site is generally bounded by Greens Bayou (P100-00-00) to the west, Spicewood Ln to the north, CE King Parkway to the east and the Beaumont Freeway (Business US 90) to the south. The local drainage system is composed of roadside ditches less than two feet deep and driveways culverts. The proposed improvements include the design of an enclosed storm sewer system with a shallow swale above along John Ralston Road. The project also includes a wet bottom detention basin to mitigate adverse impacts not only for the Ralston Acres project but also for a portion of the Houmont Park Drainage Improvements project proposed to the north and east of subdivision. This agreement will provide Professional Services from the Engineer of Record during construction phase.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Ralston Acres community. No impact on project schedule or cost anticipated.

 

Alternative Options:

If no action is taken, the engineer of record will not be accessible for support through the construction of the project.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/29/2019

1.g.4

Contract Award for Professional Engineering Services with Walter P Moore and Associates, Inc.

08/13/2019

1.n.4

Recommendation that that the court approve study reports prepared by Walter P. Moore & Associates, Inc.

01/07/2020

1.f.3

Contract Award for Professional Engineering Services with CivilTech Engineering, Inc.

08/24/2021

98 (21-4473)

Contract Amendment - CivilTech Engineering, Inc.

03/08/2022

100 (22-1525)

Public Necessity

03/22/2022

34 (22-1999)

Contract Amendment - CivilTech Engineering, Inc.

08/02/2022

80 (22-4635)

Public Necessity

11/15/2022

54 (22-7211)

Contract Amendment - CivilTech Engineering, Inc.

01/10/2023

82 (23-0074)

Financial Authorization

12/19/2023

47 (23-7288)

Contract Amendment - Woolpert, Inc.

05/07/2024

55 (24-2751)

Contract Amendment - Woolpert, Inc.

12/10/2024

136 (24-7650)

Request for approval of a Study Report prepared by Woolpert, Inc

 

Location: Ralston Acres Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109

$

$352,481.40

$352,481.40

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$352,481.40

$352,481.40

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$352,481.40

$352,481.40

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/9/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer

 

Attachments (if applicable): Construction Phase Services Agreement