Legislation Details

File #: 26-1731    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 3/5/2026 In control: Commissioners Court
On agenda: 3/19/2026 Final action: 3/19/2026
Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Platinum Paving, LLC, in connection with Pedestrian Improvements - Various Locations - 2023, Job No. 24/0260, UPIN 24208MF33Z01, Precinct 3.

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

 

Project ID (if applicable): Job No. 24/0260, UPIN 24208MF33Z01

Vendor/Entity Legal Name (if applicable): Platinum Paving, LLC

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Transmittal by the Office of the County Engineer of a substantial completion certificate with Platinum Paving, LLC, in connection with Pedestrian Improvements - Various Locations - 2023, Job No. 24/0260, UPIN 24208MF33Z01, Precinct 3.

end

 

Background and Discussion:

The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset.  The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001.  These certificates provide a method by which Harris County may document and record this date.

 

Expected Impact:

This action establishes the date on which a capital improvement enters service as a Harris County asset.

 

 

 

 

 

 

Alternative Options:

There is no other alternative available except the requested changes will allow the contractor to complete the proposed work according to the design plan and complete the project.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/19/2024

315 (24-5738)

Contract Award

05/22/2025

81 (25-3210)

Contract Amendment #1 for additional funds and extension of project term

12/11/2025

25 (25-7536)

Contract Amendment #2 for additional funds and extension of project term

12/11/2025

26 (25-7538)

Contract Amendment #2 for additional funds and extension of project term

 

Location:

Address (if applicable): Various Locations

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

1070 - Mobility Fund

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 3/19/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): Substantial Completion Form

.