Legislation Details

File #: 26-7034    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/13/2026 In control: Commissioners Court
On agenda: 10/29/2026 Final action: 10/29/2026
Title: Request for approval of a change in contract with MC2 Civil, LLC, in connection with final construction of Roadway Maintenance - Asphalt Package - 2 - 2025, adding 9 calendar days, with a deduction in the amount of $871,938.69, Job No. 25/0419-1, UPIN 25103MF3MW01, Precinct 3, MWBE Contracted Goal: 30.33%, MWBE Current Participation: 46.18%.

Harris County Commissioners Court

Request for Court Action

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 25/0419, UPIN 25103MF3MW01

Vendor/Entity Legal Name (if applicable): MC2 Civil, LLC

 

MWBE Contracted Goal (if applicable): 30.33%

MWBE Current Participation (if applicable): 46.18%

Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with MC2 Civil, LLC, in connection with final construction of Roadway Maintenance - Asphalt Package - 2 - 2025, adding 9 calendar days, with a deduction in the amount of $871,938.69, Job No. 25/0419-1, UPIN 25103MF3MW01, Precinct 3, MWBE Contracted Goal: 30.33%, MWBE Current Participation: 46.18%.

end

 

Background and Discussion:

This project consists of base repair, milling and overlay, striping, and traffic signal loop improvements along Hargrave Road from SH 249 to Falba Road, approximately 5,200 feet (0.99 miles), and along Dowdell Road from Kuykendahl Road to FM 2920, approximately 9,900 feet (1.9 miles).

 

This change in Contract includes:

(PCO #1, RFI #4) MC2 is requesting a 9-calendar-day contract extension with no additional compensation.  The request is primarily due to multiple rain-out days during the 47-day contract period, as well as schedule impacts from performing concurrent roadway and driveway work.

 

Expected Impact:

The expected impact is to reconcile the contract time with documented project delays and provide the additional time that was necessary to complete the remaining work.

 

Alternative Options:

None at this time.

 

County Strategic Plan Goal: N/A

County Strategic Plan Objective: N/A Justice/Safety Initiative (Goal 1): N/A Infrastructure Initiative (Goal 2): N/A Economy Initiative (Goal 3): N/A Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

02/26/2026

292 (26-1535)

Contract Award

09/17/2026

496 (26-5905)

Substantial Completion

 

Location:

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources:

Existing Budget

1070 - Mobility Fund

$

-$871,938.69

-$871,938.69

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$871,938.69

-$871,938.69

$

Additional Budget Request (Requires Fiscal Review Request Form)

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

 

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$871,938.69

-$871,938.69

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

 $

 $

 $

 

Local Match Source - Additional Budget Request: Choose an item.

 $

 $

 $

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 10/29/2026

Anticipated Implementation Date (if different from Court date): N/A

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B