File #: 25-3683    Version: 1 Name:
Type: Contract - Renewal Status: Passed
File created: 6/2/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval of a renewal option with Autoarch Architects, LLC at a cost of $1,500,000; Collaborative Engineering Group $1,500,000; Concept Engineers, Inc. $1,000,000; Dally + Associates, Inc. $1,000,000; Huitt-Zollars, Inc. $1,250,000; Johnston, LLC $1,000,000; JQ Infrastructure, LLC $1,000,000; JZ Interior Design, LLC $1,000,000; Kimley-Horn and Associates, Inc. $1,000,000; MWA Architects, Inc. $1,000,000; Page Southerland Page, Inc. (Page) $1,500,000; PDG, Inc. dba PDG Architects $1,000,000; PGAL, Inc. $1,500,000; Powers Brown Architecture NA, LLC $1,000,000; RDLR Architects $1,700,000; Salas O'Brien $1,000,000; Tessere, Inc. $1,000,000; TLC Engineering, Inc. $1,000,000; Walter P. Moore and Associates, Inc. $1,000,000; WSP USA Environment & Infrastructure Inc $1,000,000; and Ziegler Cooper Architects $1,000,000 for professional architectural and/or engineering services for facility maintenance, repairs, and rehabilitation for Harris County for the period of June 14, 2025 - June 13, 2026 (210160), MWBE Contracted Goal: 20%.
Attachments: 1. 25-3683 Job No. 210160 Renewal - Multiple Vendors.pdf

Primary Department: Purchasing

Primary Department Head/Elected Official: Paige McInnis

 

Secondary Department: County Engineer

Secondary Department Head/Elected Official: Milton Rahman

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Renewal

 

Project ID (if applicable): 210160

Vendor/Entity Legal Name (if applicable): Autoarch Architects, LLC; Collaborative Engineering Group; Concept Engineers, Inc.; Dally + Associates, Inc.; Huitt-Zollars, Inc.; Johnston, LLC; JQ Infrastructure, LLC; JZ Interior Design, LLC ; Kimley-Horn and Associates, Inc.; MWA Architects, Inc.; Page Southerland Page, Inc. (Page); PDG, Inc. dba PDG Architects; PGAL, Inc.; Powers Brown Architecture NA, LLC ; RDLR Architects;

Salas O’Brien; Tessere, Inc.; TLC Engineering, Inc.; Walter P. Moore and Associates, Inc.; WSP USA Environment & Infrastructure Inc; Ziegler Cooper Architects

 

MWBE Contracted Goal (if applicable): 20%

MWBE Current Participation (if applicable): See background

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

 

Request Summary (Agenda Caption):

title

Request for approval of a renewal option with Autoarch Architects, LLC at a cost of $1,500,000; Collaborative Engineering Group $1,500,000; Concept Engineers, Inc. $1,000,000; Dally + Associates, Inc. $1,000,000; Huitt-Zollars, Inc. $1,250,000; Johnston, LLC $1,000,000; JQ Infrastructure, LLC $1,000,000; JZ Interior Design, LLC $1,000,000; Kimley-Horn and Associates, Inc. $1,000,000; MWA Architects, Inc. $1,000,000; Page Southerland Page, Inc. (Page) $1,500,000; PDG, Inc. dba PDG Architects $1,000,000; PGAL, Inc. $1,500,000; Powers Brown Architecture NA, LLC $1,000,000; RDLR Architects $1,700,000; Salas O’Brien $1,000,000; Tessere, Inc. $1,000,000; TLC Engineering, Inc. $1,000,000; Walter P. Moore and Associates, Inc. $1,000,000; WSP USA Environment & Infrastructure Inc $1,000,000; and Ziegler Cooper Architects $1,000,000 for professional architectural and/or engineering services for facility maintenance, repairs, and rehabilitation for Harris County for the period of June 14, 2025 - June 13, 2026 (210160), MWBE Contracted Goal: 20%.

end

 

Background and Discussion:

Request for approval of a renewal option with PGAL, Inc.; Page Southerland Page, Inc. (Page); Huitt-Zollars, Inc.; PDG, Inc. dba PDG Architects; Tessere, Inc.; RDLR Architects; Dally + Associates, Inc; Walter P. Moore and Associates, Inc.; Salas O'Brien; AutoArch Architects, LLC; joh & Company Architects; Concept Engineers, Inc.; Ziegler Cooper Architects; JQ Infrastructure, LLC; MWA Architects, Inc.; Powers Brown Architecture NA, LLC; TLC Engineering, Inc.; Collaborative Engineering Group; JZ Interior Design, LLC; WSP USA Environment & Infrastructure Inc.; and Kimley-Horn and Associates, Inc.; Johnston, LLC for professional architectural and/or engineering services for facility maintenance, repairs, and rehabilitation for Harris County for the period of June 14, 2025 - June 13, 2026, at an initial cost of $4,000,000 (210160), MWDBE Contracted Goal: 20%. MWBE Goal Participation:

Multi-Award

MWBE Goal

MWBE Participation

Autoarch Architects, LLC

 20%

100%

Collaborative Engineering Group

 20%

100%

Concept Engineers, Inc.

 20%

100%

Dally + Associates

 20%

0%

Huitt-Zollars, Inc.

20%

0%

Johnston, LLC

20%

0%

JQ Infrastructure, LLC

20%

0%

JZ Interior Design, LLC

20%

0%

Kimley-Horn and Associates, Inc.

20%

0%

MWA Architects, Inc.

17.8%

0%

Page Southerland Page, Inc. (Page)

20%

0%

PDG, Inc. dba PDG Architects

20%

0%

PGAL, Inc.

20%

0%

Powers Brown Architecture NA, LLC

13.3%

0%

RDLR Architects

20%

100%

Salas O'Brien

20%

0%

Smith & Company Architects

13.3%

0%

Tessere, Inc.

 20%

0%

TLC Engineering, Inc.

20%

100%

Walter P. Moore and Associates, Inc.

20%

0%

WSP USA Environment & Infrastructure Inc

20%

0%

Ziegler Cooper Architects

20%

0%

 

On-Call contract to be used for Facility Maintenance, Repairs, and Rehabilitation of Harris County facilities

countywide

 

Expected Impact:

Maintaining the scheduled maintenance required for existing Harris County facilities.

 

Alternative Options:

Defer regular maintenance and/or bid each project individually.

 

County Strategic Plan Goal:  Choose an item.

County Strategic Plan Objective: Choose an item.

Justice/Safety Initiative (Goal 1):  Choose an item.

Infrastructure Initiative (Goal 2):  Choose an item.

Economy Initiative (Goal 3): Choose an item.

Health Initiative (Goal 4): Choose an item.

Climate/Resilience Initiative (Goal 5): Choose an item.

Housing Initiative (Goal 6): Choose an item.

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

6/14/2022

210

Agreements Approved in Commissioners Court

6/6/2023

212

Contract Renewal No. 1

6/4/2024

328

Contract Renewal No. 2

 

Location:

Address (if applicable):

Precinct(s): Countywide

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/12/2025

Anticipated Implementation Date (if different from Court date): 6/14/2025

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Debjani Chakravarty, Director, Contracts & PMO, Office of the County Engineer, Sheila Rodriguez, Senior Buyer, Purchasing

 

Attachments (if applicable): Letter