Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Termination
Project ID (if applicable): UPIN 211033961530014
Vendor/Entity Legal Name (if applicable): Gunda Corporation, LLC
MWDBE Contracted Goal (if applicable):0
MWDBE Current Participation (if applicable):NA
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a Mutual Termination Agreement with Gunda Corporation, LLC for improvements to the Westgreen Boulevard Segment 1 - from Morton Road to Clay Road Project, Precinct 4 (Previously Precinct 3), UPIN 211033961530014, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
The professional Services contract was originally executed on 12/14/2021 with Gunda Corporation, LLC and no amendment was made to the contract. This project has been mutually agreed upon for termination. UPIN 211033961530014, Precinct 4
Expected Impact: Termination of the agreement and return of the remaining funds.
Alternative Options: No alternative option. Both parties agree to mutually terminate the agreement.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
12/14/2021 |
30. |
Recommendation that the County Judge execute amendments/agreements with: Gunda Corporation, LLC, in the amount of $659,905.60 for engineering services for improvements to Westgreen Boulevard Segment 1 - from Morton Road to Clay Road in Precinct 4 (UPIN 211033961530014). |
Location:
Address (if applicable):
Precinct(s): Precinct 4
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
FY 24 |
FY 25 |
Next 3 FYs |
|
Incremental Expenditures (do NOT write values in thousands or millions) |
|
Labor Expenditures |
$ |
$ |
$ |
|
Non-Labor Expenditures |
$(297,472.00) |
$ |
$ |
|
Total Incremental Expenditures |
$(297,472.00) |
$ |
$ |
|
Funding Sources (do NOT write values in thousands or millions) |
|
Existing Budget |
|
Other |
$(297,472.00) |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Total Current Budget |
$(297,472.00) |
$ |
$ |
|
Additional Budget Requested |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Total Additional Budget Requested |
$ |
$ |
$ |
|
Total Funding Sources |
$( 297,472.00) |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
|
Additional Positions Requested |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
Anticipated Court Date: January 30, 2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Hatem Elbastawisy, PE - (Interim) Senior Director of Project Delivery - Harris County Engineering Department
Attachments (if applicable): Agreement