Title: Request for approval of change order 29 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,230,610.76 to $24,305,044.95, adding 48 calendar days, MWDBE Contracted Goal: 35%.

Department: Housing and Community Development

Department Head/Elected Official: Thao Costis

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Financial Authorization

 

Project ID (if applicable): D2017-088; HAY Center Campus

Vendor/Entity Legal Name (if applicable): Arch-Con Corporation

 

MWDBE Contracted Goal (if applicable): 35%

MWDBE Current Participation (if applicable):

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of change order 29 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,230,610.76 to $24,305,044.95, adding 48 calendar days, MWDBE Contracted Goal: 35%.

end

 

Background and Discussion:

This project includes new construction of two buildings and site development on a 3.268-acre site at 3131 Gulf Freeway. The residential building is a three story 50-unit building for youth aging out of foster care with community space, kitchen, a small gym, a business center, and private study rooms. The other building is a one-story commercial building for wrap-around services, including huddle/meeting rooms, a computer lab, life skills training rooms, administrative offices, administrative and building support.  The two buildings are connected by a covered walkway. Site development includes underground detention below surface parking and outdoor landscaped areas.

 

Expected Impact:

Changes allow the completion of the project in accordance with the original intent of the project. Changes include increasing the construction contract from $24,230,610.76 to $24,305,044.95. This request will be funded by the already approved 2017 CDBG-DR funds for the residential building portion and treasury ARPA funds for the services building portion.

 

Alternative Options:

Commissioners court could delay approval, not allowing the project to be completed as intended.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

X Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/13/2022

P.47 395

Request for approval of an award on the basis of only bid to Arch-Con Corporation in the amount of $23,356,200 for construction for a new service and residential buildings at the HAY Center Foundation in Precinct 1, and for the County Clerk to execute any applicable bonds to be received (220335), MWDBE Contracted Goal: 35%

9/19/2023

#20

Request for approval of change orders 1, 2, 3, and 4 for the HAY Center Project and to increase the construction contract with ARCH-Con Corporation from $23,356,200 to $23,879,532.01.

1/30/2024

#25

Request for approval of change orders 5,6,7,8,9,10,11,12,12,14 and 15 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $23,879,532.01 to $24,050,607.34, MWDBE Contracted Goal: 35%.

8/27/2024

p.19; 173

Request for approval of change orders 16, 17, 18, 19, 20, 21, 22 and 23 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,050,607.34 to $24,182,716.04, MWDBE Contracted Goal: 35%.

8/27/2024

p.19; 174

Request for approval of change orders 24, 25, 26, 27, and 28 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,182,716.04 to $24,230,610.76.

 

Location:

Address (if applicable): 3131 Gulf Freeway, Houston, Texas 77003

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Affordable Rental Housing

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Grant

$

$74,434.19

$74,434.19

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$74,434.19

$74,434.19

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$74,434.19

$74,434.19

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: November 12, 2024

 

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Sam Borders, Director, Multi- Family Housing Development, Harris County Housing and Community Development

 

Attachments (if applicable): Change Orders: 29: PCP-37, PCP-38, PCP-39, PCP-40, PCP-41, PCP-43, PCP-46.