File #: 25-2642    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 4/23/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action: 5/8/2025
Title: Request for approval of a change in contract with Sapo Engineering Consultants, in connection with final construction of Sidewalks and Undercrossing Project - Huffmeister, adding 61 calendar days, with a deduction in the amount of $28,815.79, Job No. 23/0340-1, UPIN 20103N302902, Precinct 3, MWBE Contracted Goal: 32%, MWBE Current Participation: 100%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0340, UPIN 20103N302902

Vendor/Entity Legal Name (if applicable): Sapo Engineering Consultants

 

MWBE Contracted Goal (if applicable): 32%

MWBE Current Participation (if applicable): 100%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Sapo Engineering Consultants, in connection with final construction of Sidewalks and Undercrossing Project - Huffmeister, adding 61 calendar days, with a deduction in the amount of $28,815.79, Job No. 23/0340-1, UPIN 20103N302902, Precinct 3, MWBE Contracted Goal: 32%, MWBE Current Participation: 100%.

end

 

Background and Discussion:

The project involves the construction of a 5-foot-wide concrete sidewalk, featuring wheelchair ramps at all public street intersections, properly sloped driveways, and retaining walls as needed to address steep grades behind the curb.  Oversight was provided by the Harris County Office of the County Engineer’s CPD team.

 

Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.

- PCO - 4, A total of 10 additional calendar days have been granted, including 4 days for water pump issues caused by another contractor’s flooding of formwork, 3 days for delays due to Hurricane Beryl, and 3 days for continuous rain events.

- PCO - 5, An additional 5 days are being requested to adjust the traffic pull box in preparation for the sidewalk pour.

- PCO - 6, An additional 46 days were granted due to insufficient planning and execution.

- PCO - 7, Final Adjustment $28,815.79

 

 

Expected Impact:

Changes allow for addition of new bid items to complete the project in accordance with the original intent of the project and in compliance with precinct requests.

 

Alternative Options:

No alternative options.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  G1: Expand pedestrian and cyclist infrastructure on County-managed roads,

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/30/2024

310 (24-0488)

Contract Award

 

Location:

Address (if applicable): 11507 Huffmeister Rd, Houston, TX 77065

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 2601

$

-$28,815.79

-$28,815.79

$

Choose an item.

$

$

$

$

Choose an item.

$

-$28,815.79

-$28,815.79

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$28,815.79

-$28,815.79

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/8/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B