Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Y. Stuckett, P.E., CFM, Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): S500-02-00-E001
Vendor/Entity Legal Name (if applicable): Texas Department of Transportation
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an advance funding agreement with the Texas Department of Transportation, in the amount of $529,764.35, for voluntary local agreement contributions by the Flood Control District to improve drainage and reduce flood risks in connection with transportation improvement projects with no required match on-system (Luce Bayou Watershed, Bond ID F-108, Project ID S500-02-00-E001, Agreement No. 2022-194, Precinct 3).
end
Background and Discussion:
The Flood Control District is working on a flood damage reduction project in the same area where uncontrolled sheet flow is the main cause of inundation impacting the Commons Area and several roads, including FM2100. It was decided to partner with (Texas Department of Transportation) TxDOT to assist with the construction of an 8’X8’ RCB within TxDOT right-of-way to intercept, redirect and detain the sheet flow within the proposed Flood Control District and TxDOT detention basins. The basins will be interconnected and will have a common outfall to Luce Bayou. TxDOT is constructing most of the structural components such as the RCBs and outfalls for HCFCD using their current construction contract. This Amendment will provide for the addition cost to the outfall pipe resulting in a Change Order due to an increase in the size of the pipe in the original agreement for Huffman Cleveland Stormwater Detention Basin
Expected Impact:
The project seeks to reduce flood risks and strengthen resiliency in the Luce Bayou watershed by providing additional flow from sheet flow.
Alternative Options:
The alternative to approving this item would be not to provide the shared cost for the outfall agreement., which would result in sharing our agreed commitment.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
11/29/2022 |
78. |
Agreement |
Location: FM 2100 Huffman Cleveland Road
Address (if applicable):
Precinct(s): Precinct 3
|
Fiscal and Personnel Summary |
|
Service Name |
4.a.2 - Construction Services |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Bonds |
$ |
$529,764.35 |
$529,764.35 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$529,764.35 |
$529,764.35 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$529,764.35 |
$529,764.35 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 11/19/2026
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District
Attachments (if applicable): Agreement