File #: 26-0939    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 1/29/2026 In control: Commissioners Court
On agenda: 2/12/2026 Final action: 2/12/2026
Title: Request for approval of an award on the basis of low bid to Brice Construction & Design, LLC in the amount of $1,428,556 for water line rehabilitation at Deussen Park for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (250393), MWBE Contracted Goal: 20.74%.

Primary Department: Purchasing

Primary Department Head/Elected Official: Kimberly J. Williams, JD

 

Secondary Department: Commissioner, Precinct 1

Secondary Department Head/Elected Official: Rodney Ellis

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable):250393

Vendor/Entity Legal Name (if applicable): Brice Construction & Design, LLC

 

MWBE Contracted Goal (if applicable): 20.74%

MWBE Current Participation (if applicable):

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

 

Request Summary (Agenda Caption):

title

Request for approval of an award on the basis of low bid to Brice Construction & Design, LLC in the amount of $1,428,556 for water line rehabilitation at Deussen Park for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (250393), MWBE Contracted Goal: 20.74%.

end

 

Background and Discussion:

The existing water system at Alexander Deussen Park experiences frequent breaks and leakage. The system is currently supplied by a well located on the adjacent City of Houston property. A comprehensive evaluation of the park’s existing utility systems recommended replacing the existing water mains and service lines. This project will replace and upsize the existing water main within the Deussen Park limits, including the supply line from the City of Houston water well to the terminus of the park.

 

Expected Impact:

The failing water system in Alexander Deussen Park can be replaced with a reliable system and minimize maintenance costs.

 

Alternative Options:

If the request is not approved, then the failing water system will not be replaced, and the Precinct will continue to incur high maintenance costs due to numerous water leaks of the aging water system.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H4: Consistently embed sustainability considerations in the project planning and design process.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

3-27-25

116/25-1990

Approved to amend an agreement with Binkley and Barfield Inc. for additional On-Call - Professional Services and to add a survey subconsultant in connection with various projects in Precinct 1.

12-18-25

55/25-8005

Transmittal by the Office of the Purchasing Agent of a project scheduled for advertisement for water line rehabilitation at Deussen Park for Precinct 1 (250393).

 

Location:

Address (if applicable): Alexander Deussen Park and City of Houston property (13501 Aquaduct Rd, Houston TX 77044)

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3239

$

$ 1,428,556.00

$1,428,556.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$1,428,556.00

$1,428,556.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$1,428,556.00

$1,428,556.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 2/12/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer; Maria Heinzmann, Senior Buyer, Harris County Purchasing

 

Attachments (if applicable): Award Documents