File #: 26-0943    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 1/29/2026 In control: Commissioners Court
On agenda: 2/12/2026 Final action: 2/12/2026
Title: Request for approval to execute an interlocal agreement with Bridgeland Management District to evaluate feasibility of constructing a 3.2-mile trail on an existing CenterPoint Easement between Jack Road and John Paul Landing Park, UPIN 26104MF3YC01, Precinct 4.
Attachments: 1. 26-0943-ILA-26104MF3YC01-CenterPointTrailFeasibilityStudy-Bridgeland-P4-2.12.26 Agmt

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: Commissioner, Precinct 4

Secondary Department Head/Elected Official: Lesley Briones

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

 

Project ID (if applicable): UPIN 26104MF3YC01

Vendor/Entity Legal Name (if applicable): Bridgeland Management District

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  Exempt - Interlocal/Cooperative Agreement

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an interlocal agreement with Bridgeland Management District to evaluate feasibility of constructing a 3.2-mile trail on an existing CenterPoint Easement between Jack Road and John Paul Landing Park, UPIN 26104MF3YC01, Precinct 4.

end

Background and Discussion:
Bridgeland is a forthcoming master-planned community in Cypress, Texas, located in unincorporated Harris County. The Trail, outlined in Bridgeland's Land Plan, will generally follow the CenterPoint easement, approximately 8 feet wide, with alignment adjustments made if needed for transmission lines. The proposed CenterPoint Trail will link the planned Creekland Village and Prairieland Village.

 

Expected Impact:

This project will provide multi-modal and active transportation connections in the Bridgeland community. It will also provide enhanced bike/ped connectivity from Bridgeland to John Paul Landing Park, improved drainage and environmental benefits to the region.

 

Alternative Options:

 

Harris County can search for other alternative options.

 

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): Jack Road and John Paul Landing Park

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$245,000.00

$245,000.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$245,000.00

$245,000.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$245,000.00

$245,000.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 2/12/2026

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Lauren Valdes, Assistant Director, Business Services - OCE

 

Attachments (if applicable): Interlocal Agreement