File #: 25-3428    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/27/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval of a change in contract with John Reed and Company, LLC in connection with Brays Bayou Pedestrian/Bike Bridge near Stella Link/Glen Arbor, adding 60 calendar days, with an addition in the amount of $70,203.97, Job No. 23/0286-4, UPIN 19101MF0XZ01, Precinct 1, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No: 23/0286, UPIN 19101MF0XZ01

Vendor/Entity Legal Name (if applicable): John Reed and Company, LLC

 

MWBE Contracted Goal (if applicable): 0%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  0% - Non-Divisible

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with John Reed and Company, LLC in connection with Brays Bayou Pedestrian/Bike Bridge near Stella Link/Glen Arbor, adding 60 calendar days, with an addition in the amount of $70,203.97, Job No. 23/0286-4, UPIN 19101MF0XZ01, Precinct 1, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.

end

 

Background and Discussion:

The project is to construct a pedestrian bridge over Brays Bayou to connect the pedestrian facilities from North Braeswood Boulevard to South Braeswood Boulevard, east of Stella Link Road.  The bridge has 3-spans with 226 feet length and approximate 400 feet ramps.

 

Expected Impact:

Provide safe pedestrian and cyclist crossing over Brays Bayou between North Braeswood Boulevard to South Braeswood Boulevard.

 

Alternative Options:

N/A

 

 

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  G1: Expand pedestrian and cyclist infrastructure on County-managed roads,

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/19/2023

325 (23-5453)

Contract Award

06/04/2024

83 (24-3051)

Contract Amendment #1 for additional funds

01/09/2025

37 (25-0070)

Contract Amendment #2 for extension of project term

03/27/2025

105 (25-2026)

Contract Amendment #3 for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3002

$

$70,203.97

$70,203.97

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$70,203.97

$70,203.97

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$70,203.97

$70,203.97

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/12/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 