Legislation Details

File #: 26-2289    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 4/1/2026 In control: Commissioners Court
On agenda: 4/16/2026 Final action: 4/16/2026
Title: Request for approval to execute an agreement with WSB, LLC. in the amount of $64,244.00 for Professional Engineering services in connection with Asphalt Rehabilitation - Campbell Road - 2025, UPIN 25103MF3N001, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
Attachments: 1. Award-CPS-25103MF3N001-Asphalt Rehabilitation-Campbell Rd-2025-WBS-P3-4.9.26.pdf

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: Commissioner, Precinct 3

Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 25103MF3N001

Vendor/Entity Legal Name (if applicable): WSB LLC.

 

MWBE Contracted Goal (if applicable): 0%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  0% - Non-Divisible

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with WSB, LLC. in the amount of $64,244.00 for Professional Engineering services in connection with Asphalt Rehabilitation - Campbell Road - 2025, UPIN 25103MF3N001, Precinct 3, Justification for 0% MWBE Participation Goal:  0% - Non-Divisible.

end

 

Background and Discussion:

 

Precinct 3 is requesting the Office of the County Engineer to approve an agreement to provide construction phase services for Campbell Road mill and overlay with base repairs on the southern segment and complete reconstruction on the north segment.

 

Expected Impact:

 

 The asphalt maintenance improvements will improve road quality and connectivity for the community in the specified area.

 

Alternative Options:

 

The alternative is not to complete the maintenance, and the road will continue to operate with the existing conditions.

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): Campbell Road, between Clay Rd and Hempstead Hwy

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other

$

$64,244.00

$ 64,244.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$ 64,244.00

$ 64,244.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$ 64,244.00

$ 64,244.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 4/16/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer

 

Attachments (if applicable): Contract and Exhibits