Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 22101MF2F801
Vendor/Entity Legal Name (if applicable): Scientech Engineers Inc.
MWDBE Contracted Goal (if applicable): 7%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Scientech Engineers Inc. in the amount of $154,844 for Construction Phase Services in connection with West Canal Pedestrian Bridge at Aqueduct Road as part of Alexander Deussen and Dwight D. Eisenhower Park Improvements, UPIN 22101MF2F801, Precinct 1, MWDBE Contracted Goal: 7%.
end
Background and Discussion:
The project is to construct a two span, signature pedestrian bridge with parapet panel over West Canal (owned by Coastal Water Authority) at Aqueduct Road to provide the pedestrian, hike and bike connection between Deussen Park and Eisenhower Park as part of the park trail system. The pedestrian bridge project is part of Deussen and Eisenhower Park Improvement project.
Expected Impact:
This project provides the safe and convenient connection for both cyclist and pedestrian between two parks.
Alternative Options:
If no action is taken, the engineer of record will not be accessible for support through the construction of the project.
Alignment with Goal(s):
X_ Justice and Safety
_ Economic Opportunity
_ Housing
X_ Public Health
X Transportation
_ Flooding
_ Environment
X_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
09/24/19 |
1.d.1 |
Court Approved ATN for Scientech Engineers, Inc. |
|
01/28/20 |
1.g.2 |
Agreement for Study and Design |
|
08/24/21 |
95 |
Amendment No. 1 |
|
01/31/23 |
41 |
Amendment No. 2 |
Location:
Address (if applicable): West Canal at Aqueduct Road
Precinct(s): Precinct 1
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Bonds |
$ |
$154,844 |
$154,844 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$154,844 |
$154,844 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$154,844 |
$154,844 |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: July 15, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., Senior Director of Capital Project Infrastructure, HCED