Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 24102MF3AT01
Vendor/Entity Legal Name (if applicable): MBCO Engineering LLC
MWBE Contracted Goal (if applicable): 19.60%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with MBCO Engineering, LLC in the amount of $498,121.60 for professional engineering services in connection with Corridor Study - Milby Street - 2023 - UPIN 24102MF3AT01, Precinct 2, MWBE Contracted Goal: 19.60%.
end
Background and Discussion:
Harris County Precinct 2 (PCT2) has submitted a request to Harris County Engineering Department (HCED) PMO to manage the Milby Street Corridor Study. This project spans approximately 1.32 miles, from Polk Street to Marron Park, and is part of Precinct 2's collaboration with the East End District. The study, aligned with Revive2Thrive vision, aims to enhance safety and improve quality of life by evaluating and upgrading existing infrastructure. The study will focus on assessing roadways, drainage systems, traffic patterns and sidewalk conditions along Milby Street within the project limits.
Expected Impact:
Engaging MBCO Engineering will accelerate the assessment of current roadway, drainage, and pedestrian infrastructure along the corridor. The findings will guide future improvements and ensure integration of pedestrian and bicycle-friendly features, promoting safety and long-term economic growth within the area.
Alternative Options: If no action is taken, professional engineering services will be delayed.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): G1: Expand pedestrian and cyclist infrastructure on County-managed roads,
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan:
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
03/26/2024 |
24-1539 |
Request for approval to negotiate with MBCO Engineering LLC for Professional Engineering Services in connection with Study & Design of on-street bike lane routes along Milby Street from Polk Street to Tony Marron Park; and Forest Hill Blvd and 72nd Street from Briscoe Elementary School to Avenue H, UPIN 24102MF3AT01, Precinct 2. |
Location:
Address (if applicable): Milby Street
Precinct(s): Precinct 2
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
1070 - Mobility Fund |
$ |
$498,121.60 |
$498,121.60 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$498,121.60 |
$498,121.60 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$498,121.60 |
$498,121.60 |
$ |
|
Grants - Proposed Budget (To be filled out by Grants staff only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 8/26/2025
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Truitt Rounsavall, P.E., PMP, MBA, LSSBB (Interim) Director of Capital Projects, Horizontal, Office of the County Engineer