File #: 26-6281    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 9/9/2026 In control: Commissioners Court
On agenda: 9/22/2026 Final action:
Title: Request for approval of a change in contract with Millis Equipment, LLC, in connection with final construction of Hufsmith-Kohrville Rd 2, with a deduction in the amount of $1,577,806.51, Job No. 23/0308-7, UPIN 15104M23NP02, Precinct 3, MWBE Contracted Goal: 28.50%, MWBE Current Participation: 30.95%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0308, UPIN 15104M23NP02

Vendor/Entity Legal Name (if applicable): Millis Equipment, LLC

 

MWBE Contracted Goal (if applicable): 28.50%

MWBE Current Participation (if applicable): 30.95%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Millis Equipment, LLC, in connection with final construction of Hufsmith-Kohrville Rd 2, with a deduction in the amount of $1,577,806.51, Job No. 23/0308-7, UPIN 15104M23NP02, Precinct 3, MWBE Contracted Goal: 28.50%, MWBE Current Participation: 30.95%.

end

 

Background and Discussion:

 

Project included the reconstruction of Hufsmith-Kohrville Road from Hollow Glen Lane to 500' North of Ezekiel from 2 lane asphalt road to 4 lane concrete curb and gutter boulevard with 32' raised median with traffic signals at Lacey Road and Ezekiel Road.  There are two outfalls within limits of the project, North Pointe Boulevard and Champion Wood Drive detention ponds.  The requested change order is necessary to compensate the contractor for additional scope.  These changes materially altered the original scope, cost, and schedule, warranting appropriate contract adjustment.

 

The change in contract includes the following:

                     The final adjustment (reconciliation of actual quantities used in construction against the bid

                     quantities). -$1,577,806.51).

 

 

 

Expected Impact:

This change will allow the Contractor to be properly compensated for the additional work.

 

Alternative Options:

Conduct thorough pre-construction assessments and detailed utility mapping to identify and mitigate potential conflicts early.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Date

Agenda Item #

Action Taken

11/14/2023

204 (23-6678)

Contract Award

06/25/2024

56 (24-3584)

Contract Amendment for additional funds

09/19/2024

51 (24-5681)

Contract Amendment for additional funds and extension of project term

02/06/2025

83 (25-0840)

Contract Amendment for additional funds and extension of project term

10/16/2025

27 (25-6155)

Contract Amendment for additional funds and extension of project term

06/11/2026

23 (26-3572)

Contract Amendment for additional funds

 

Prior Court Action (if any):

 

Location:

Address (if applicable): Hufsmith-Kohrville Rd from Hollow Glen Lane to 500' North of Ezekiel

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109, 3002

$

-$1,577,806.51

-$1,577,806.51

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$1,577,806.51

-$1,577,806.51

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$1,577,806.51

-$1,577,806.51

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

$

$

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 9/22/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B