Primary Department: Flood Control District
Primary Department Head/Elected Official: Marcus Stuckett, P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of the executed amendment to the agreement with the Texas General Land Office to approve revised project details for two projects in the CDBG-DR Program (24-033-000-E072).
end
Background and Discussion:
On June 6, 2023, Commissioners Court approved a list of potential CDBG-DR projects under direct allocation to the Flood Control District. This approval authorized the Flood Control District to begin working on project applications for the approved project list. Upon application approvals by the Texas General Land Office, the projects are required to be formally added to the CDBG-DR contract. All projects have been previously included and approved by the Texas General Land Office in prior contract amendments, while this amendment provides revised project details for two projects so we can seek reimbursement on expenditures related to these projects. This transmittal is for the Fourth Amendment to the Agreement, which includes revisions for the following projects: Dinner Creek Stormwater Detention Basin and Jackson Bayou Detention Basin.
Expected Impact:
With the approval of this amendment, the Flood Control District can continue to seek reimbursement on expenditures related to the CDBG-DR program for all projects listed, as it relates to design, environmental, and grant administration activities.
Alternative Options:
The alternative is to not amend the contract and lose opportunities to seek reimbursement or meet spending milestones
County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H2: Evaluate the feasibility and potential impacts of substantial, large-scale flood mitigation measures to provide equitable and transformational regional benefits.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
6/11/2026 |
385 |
Transmittal by the Flood Control District of the executed amendment to the agreement with the Texas General Land Office to approve one project for the CDBG-DR Program (24-033-000-E072). |
|
2/12/2026 |
240. |
Transmittal by the Flood Control District of amendment No. 3 to the agreement with the Texas General Land Office (GLO), to approve four projects for the CDBG-MIT Program (GLO Contract No. 24-064-000-E151, Project ID’s U501-06-00-E002 and U101-00-00-E002; P518-15-00-E001; P500-06-00-E008; C118-00-00-E001, Precincts 1, 2, and 4). |
|
1/8/2026 |
319. |
Transmittal by the Flood Control District of the executed amendment to the agreement with the Texas General Land Office (GLO), to approve seven additional projects for the CDBG-MIT Program (GLO Contract No. 24-064-000-E151). |
|
10/16/2025 |
485. |
Transmittal by the Flood Control District of the executed amendment to the agreement with the Texas General Land Office, to approve four projects for the CDBG-MIT Program (24-064-000-E151) and increase the CDBG-MIT program award to $546,167,826 (Project ID’s G103-00-00-E003, K100-00-00-R007, K500-23-00-E005, and U501-07-00-E002, Precincts 3 and 4). |
|
9/18/2025 |
122. |
Request for approval of signatory authority as indicated within the “Depository/Authorized Signatories Designation Form” to the Executive Director for the Flood Control District or her designees regarding the CDBG-DR and CDBG-MIT programs. |
|
1/23/2025 |
77. |
Request for approval of revised project lists for use in submitting applications for Community Development Block Grant-Disaster Recovery (CDBG-DR) funds totaling up to $322 million and CDBG-Mitigation (CDBG-MIT) funds totaling up to $541.8 million. |
|
1/8/2024 |
75. |
Request for approval of signatory authority as indicated within the “Depository/Authorized Signatories Designation Form” to the Executive Director of the Flood Control District or her designees regarding the CDBG-DR and CDBG-MIT programs. |
|
10/31/2023 |
148. |
Harris County Commissioners Court approved an agreement with the GLO for CDBG-MIT funds in amount of $541,847,826. |
|
10/31/2023 |
147. |
Harris County Commissioners Court approved an agreement with the GLO for CDBG-DR funds in amount of $322,033,863. |
|
6/6/2023 |
115. |
Harris County Commissioners Court approved the presented CDBG-DR and CDBG-MIT project lists and authorized the Executive Director of the HCFCD or her designee to sign and execute Affidavit of Public Posting Forms and to sign, execute, and submit applications to the GLO to support the approved projects |
|
8/31/2022 |
1. |
Harris County Commissioners Court approved a grant agreement between the County and the Texas General Land Office (GLO) for Community Development Block Grant Mitigation (CDBG-MIT) funds in the amount of $750 million |
Location: N/A
Address (if applicable):
Precinct(s): Choose an item.
|
Fiscal and Personnel Summary |
|
Service Name |
N/A |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$ |
$ |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 9/22/2026
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District
Attachments (if applicable): Amendment