File #: 25-3255    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 5/9/2025 In control: Commissioners Court
On agenda: 5/22/2025 Final action: 5/22/2025
Title: Request for approval of a Final Investment Memo for the DCO Data Center UPS Upgrade project for an amount of $403,042 and commercial paper funding in the amount of $405,000.

Primary Department: District Clerk

Primary Department Head/Elected Official: Marilyn Burgess

Managing Department: District Clerk

Managing Department Head/Elected Official: Marilyn Burgess

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: DCO Data Center UPS Upgrade

Project ID (if applicable): TBD

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $403,042

Total Estimated Project Cost: $403,042

 

Request Summary:

title

Request for approval of a Final Investment Memo for the DCO Data Center UPS Upgrade project for an amount of $403,042 and commercial paper funding in the amount of $405,000.

end

 

Project Description:

The Harris County District Clerk’s Office is seeking funding for a Capital Improvement Project to replace and upgrade the existing Uninterruptible Power Supply (UPS) system that supports the critical infrastructure within the Harris County Civil Courthouse Data Center.

This data center serves as the central technology hub for all Harris County District Courts, County Courts at Law, and associated justice agencies, providing system access, application availability, and data services to justice employees, court staff, law enforcement partners, and the broader legal community.

The current UPS system has been in continuous operation since the opening of the Civil Courthouse in 2005. This system has reached the end of its viable service life and is scheduled to go end-of-life within the next year. Once it reaches end-of-life status, hardware support contracts will no longer be available, replacement parts will become scarce, and the risk of unplanned system failure will significantly increase.

The primary function of the UPS system is to sustain power to critical IT infrastructure during power outages - allowing systems to remain operational until building emergency generators come online. The UPS system is a cornerstone of our disaster recovery and business continuity planning, ensuring the operational resilience of justice technology services in the face of man-made or natural disasters, including hurricanes, flooding, power grid failures, or localized building incidents.

This project would fund the purchase and installation of a new, modern UPS system designed to meet current technology standards and support the County’s increasing technology demands. It will ensure that the County’s justice infrastructure is protected from power-related disruptions for years to come.

 

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Unit Price

Quantity

Estimated Cost

Estimated Completion

Galaxy VS UPS 60kW 480V with N+1 power module for external batteries, Start-up 5x8

$114,102.56

2

$228,205.12

06/30/2025

InfraStruxure PDU 60kW 208V/208V Transformerless

$16,283

2

$32,566.00

06/30/2025

Installation Accessories

$1,610

4

$6,440

06/30/2025

Freight

 

 

$2,545.68

 

Installation and removal services

 

 

$96,645.00

 

Contingency 10%

 

 

$36,640.18

 

Total

 

 

$403,041.98

-

 

Justification & Alternatives:

From an IT disaster recovery and continuity of operations (COOP) perspective, the need to replace and upgrade the District Clerk’s Data Center UPS system is both urgent and mission-critical.

The risk of continuing to operate on an end-of-life UPS system - without the availability of hardware support, replacement parts, or vendor expertise - is unacceptable given the vital role this system plays in the County's justice infrastructure.

Key Justifications:

Operational Risk: The UPS is a fundamental layer of protection against power loss for critical servers, storage, and network systems that support courtroom operations, case management systems, law enforcement connectivity, and court record access across Harris County.

 

Recent Real-World Incident: The Civil Courthouse experienced a power outage during the week of March 17, 2025. The existing UPS system performed exactly as designed, sustaining all critical IT infrastructure until building generators came online. Without a functioning UPS during this event, court operations across multiple buildings would have been disrupted, potentially resulting in mass disconnections, data loss, and operational downtime.

Disaster-Prone Region: Harris County is no stranger to natural disasters - hurricanes, flooding, and tropical storms are all well-documented threats to our region. Maintaining operational resilience against these events is a core responsibility of any disaster recovery plan.

Legal & Compliance Considerations: Alternative solutions, such as migrating the data center to an off-site public or private facility, would require years of planning, significant capital investment, and careful navigation of legal statutes, including Tex. Gov't Code § 51.304(a), which grants the District Clerk authority over the storage and management of court records.

Strategic Alignment: This project directly supports Harris County’s strategic goals of maintaining well-managed infrastructure, advancing disaster preparedness, and modernizing justice technology services across the County.

Financial Stewardship: The existing UPS system has been maintained in exceptional condition through dedicated support from the District Clerk’s IT team and vendor partners. This system has far exceeded its expected lifespan - providing nearly 20 years of service. However, continuing to defer its replacement would be fiscally irresponsible given the high risk of failure and the criticality of the systems it protects.

Stakeholders Impacted:

The beneficiaries of this project are vast and include:

•                     Harris County District Courts

•                     County Courts at Law

•                     Law enforcement agencies (local, state, federal)

•                     County Justice and Law Departments

•                     Court staff, administrative employees, and support teams

•                     Private sector legal professionals, background investigators, and research partners

•                     Citizens relying on justice services

Anticipated Impact on Other Funds (If Applicable): N/A

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.

Justice/Safety Initiative (Goal 1):  E1: Modernize data and technology architecture across the legal system.

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Decision Analysis Matrix Score (rubric on last page): 15

Previous Court Action: N/A

Date

Agenda Item #

Action Taken

 

 

 

 

 

 

 

 

 

 

Address: 201 Caroline St., Second Floor, Room 230 Houston, TX 77002

Precinct(s): Precinct 1

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$405,000

$405,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$405,000

$405,000

$

Total Funding Request

$

$405,000

$405,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/22/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Legal funding compliance confirmed by: Paige Abernathy, Assistant County Attorney, 4/30/2025 

Department Approval by: Wes McCoy, Chief Deputy of Administration

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 5/5/2025

 

Commercial Paper Request (For OMB use only):

Receiving Department: District Clerk

Project PeopleSoft ID: TBD

CP Series Description: Commercial Paper Series D can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the DCO Data Center UPS Upgrade project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.

Note: Commercial Paper is issued in increments of $5,000 and the excess is not available to be spent by the department.

OMB Financial Management contact: Amy Perez, Deputy Executive Director, Office of Management and Budget

 

Decision Analysis Matrix scoring tool - Commissioners Court has approved the rubric below for scoring capital projects. Please complete the last two rows for OMB review.

Scoring option

Strategic Plan alignment (3x weighting)

Evidence base

Impact on outcomes

Cost effectiveness

Ease of implementation

Collaboration / partnerships

Environmental sustainability

Equity

Total

-1

Antithetical to one or more aspects of the Strategic Plan

Evidence shows net negative impact on the intended goal

Impact is clearly negative

Costs expected (or shown) to outweigh benefits

County has no/limited existing capabilities and dependencies are likely to impede

Could negatively impact relationships with partners

Negatively impacts environment and/or climate change mitigation efforts

Inequitable

n/a

0

Does not align to a Strategic Objective

Evidence base is not well defined or measurable

Size of impact on one or more strategic outcomes is negligible or unclear

Net comparison is unclear

County has no/limited existing capabilities or dependencies are likely to impede

Does not involve collaboration with partners

Net neutral impact on environment and/or climate change mitigation efforts

Does not consider equity to a meaningful degree

n/a

1

Aligns to a Strategic Objective but not to a Strategic Initiative

Limited evidence-based research on outcomes; may have qualitative/theoretical support

Outcomes are defined but without target levels and/or expected impact is moderate

Moderate direct/indirect benefit relative to costs

County has existing capability to implement or dependencies are unlikely to impede

Moderately expands County leverage through collaboration with partner(s)

Marginally positive impact on environment and/or climate change mitigation efforts

Considers equity to a meaningful degree, but not comprehensively

n/a

2

Aligns to a Strategic Objective and a Strategic Initiative

Outcomes are directly supported by evidence base or credible research supports anticipated outcomes

Outcomes are clearly defined and include target levels; expected impact on outcomes is high

Significant direct/indirect benefit relative to costs

County has existing capability to implement and dependencies are unlikely to impede

Significantly expands County leverage through collaboration with partner(s)

Positively impacts environment and/or climate change mitigation efforts

Considers equity meaningfully and comprehensively

n/a

Score         (-1,0,1,2)

6

2

2

1

2

2

0

0

15

Rationale

The project aligns with G-2 and Objective R and Justice/Safe Initiative E1.

The outcome is supported by a reasonably projected higher number of residents and law enforcement served

The UPS system is a cornerstone of our disaster recovery and business continuity planning, ensuring the operational resilience of justice technology services in the face of man-made or natural disasters

The quote being consider for the project was provided by County Approved Vendor familiar with the location of the Datacenter.

The DCO Network Manager has been instrumental in the proposed project in understanding the requirements and costs involved. 

The DCO has been working together with necessary County Agencies to ensure policies and procedures are followed.

The DCO does not see a negative impact with this project proposed.

The project does not include an equity component.

n/a