Title: Request for approval of a facilities extension agreement with CenterPoint Energy Houston Electric, LLC, in the amount of $7,768, to accommodate the Little Cypress Creek Channel Conveyance Improvements between Cypress Rosehill Road and Telge Road (Little Cypress Creek Watershed, Bond ID C-15, Project ID L100-00-00-E002, Agreement No. 2024-47, Precinct 3).
Attachments: 1. 080624 AGMT CENTERPOINT 2024-47 PCT 3 backup.pdf

facilDepartment: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): CenterPoint Energy Houston Electric, LLC

Vendor/Entity Legal Name (if applicable): L100-00-00-E002

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval of a facilities extension agreement with CenterPoint Energy Houston Electric, LLC, in the amount of $7,768, to accommodate the Little Cypress Creek Channel Conveyance Improvements between Cypress Rosehill Road and Telge Road (Little Cypress Creek Watershed, Bond ID C-15, Project ID L100-00-00-E002, Agreement No. 2024-47, Precinct 3).

end

 

Background and Discussion:

The Little Cypress Creek Channel Conveyance Improvements from Cypress Rosehill Road to Telge Road project consists of improving the existing K100-00-00 channel. The project is in the Little Cypress Creek watershed where many damaging events during heavy rainfall events have occurred, and the project will help increase the capacity and flow of the existing channel. The utility agreement will help provide for the safe removal of the electrical/power facilities currently in conflict with the proposed work and will allow for safer construction of the project.

 

Expected Impact:

Upon execution of the utility agreement, the existing facilities currently in conflict will be relocated, allowing for the safe construction of future improvements to Little Cypress Creek.

 

Alternative Options:

The alternative would be to not take any action, where the facilities will remain in conflict with future improvements.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location: N/A

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

4.a.3 - Engineering Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$7,768

$7,768

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$7,768

$7,768

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$7,768

$7,768

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: August 27, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Agreement and Map