File #: 21-5411    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/4/2021 In control: Commissioners Court
On agenda: 10/12/2021 Final action: 10/12/2021
Title: Request for approval of Change in Contract No. 3 with SpawGlass Civil Construction, Inc., for the Hunting Bayou Federal Flood Risk Management Project Discrete Segment 105, Hunting Bayou Channel Improvements from US 59 to Homestead Detention Pond Outfall, adding 52 calendar days with no change to the contract amount. (Hunting Bayou Watershed, Bond ID C-18, Project ID H100-00-00-E005, Job No. 20/0192, Precinct 1).
Attachments: 1. 21-5411 CIC SPAWGLASS PCT 1

Department: Flood Control District

Department Head/Elected Official: Alan R. Black, P.E., Interim Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): H100-00-00-E005

Vendor/Entity Legal Name (if applicable): SpawGlass Civil Construction, Inc.

MWDBE Participation (if applicable): N/A

 

Request Summary (Agenda Caption):

title

Request for approval of Change in Contract No. 3 with SpawGlass Civil Construction, Inc., for the Hunting Bayou Federal Flood Risk Management Project Discrete Segment 105, Hunting Bayou Channel Improvements from US 59 to Homestead Detention Pond Outfall, adding 52 calendar days with no change to the contract amount. (Hunting Bayou Watershed, Bond ID C-18, Project ID H100-00-00-E005, Job No. 20/0192, Precinct 1).

end

 

Background and Discussion:

The purpose of this contract change is to adjust planned and projected quantities needed for current

scopes of work. The adjustment accounts for changes in scope due to unforeseen field conditions, design

directed plan revisions, and contract quantity adjustments due to quantity overruns.

 

Expected Impact:

This RCA is required in order to complete the District construction contract under original or needed

revised scope. Timely execution is appreciated in order to mitigate any potential delays from the

contractor.

 

Alternative Options:

This is an active construction contract, so there are not many alternatives to approving a change order

other than cancelling the contract which is not recommended as doing so would substantially delay the

remaining work in the construction contract.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/15/2020

18.d.11.i

Contract Award

12/15/2020

2.c.3

Contract Amendment

07/20/2021

148.

Contract Amendment

 

Location:

Address (if applicable): From US 59 to Homestead

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

4.a.2 - Construction Services

FY 21-22

Estimates

 

 

 

FY 22

Next 3 FYs

Incremental Expenditures

Labor Expenditures

-

-

-

Non-Labor Expenditures

-

-

-

Total Incremental Expenditures

-

-

-

Funding Sources (General Fund, PIC Fund, Debt or CP, Grants, or Other - Please Specify)

Existing Budget

-

-

-

-

 

-

-

-

-

 

-

-

-

-

Total Current Budget

-

-

-

Additional Budget Requested

-

-

-

-

 

-

-

-

-

 

-

-

-

-

Total Additional Budget Requested

-

-

-

Total Funding Sources

-

-

-

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

 

Anticipated Implementation Date: October 12, 2021

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Alan R. Black, P.E., Interim Executive Director

Matthew K. Zeve, P.E., Deputy Executive Director

 

Attachments (if applicable): Change in Contract and Map