Legislation Details

File #: 24-4664    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 7/24/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval of a Final Investment Memo for Emergency Generator Installations project for an initial amount of $38,900,000, including transferring $1,478,741 in authorization from the Precinct 3 Generators project, and an initial commercial paper allocation of $1,480,000 to be transferred from the Precinct 3 Generators project.
Sponsors: Mony Hossain

Department: County Engineer

Department Head: Dr. Milton Rahman, PhD., P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Emergency Generator Installations

Project ID (if applicable): TBD

Vendor Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Managing Entity: County Engineer

Incremental Authorization Requested: $38,900,000                                          

Total Estimated Project Cost: $38,900,000

 

Request Summary:

title

Request for approval of a Final Investment Memo for Emergency Generator Installations project for an initial amount of $38,900,000, including transferring $1,478,741 in authorization from the Precinct 3 Generators project, and an initial commercial paper allocation of $1,480,000 to be transferred from the Precinct 3 Generators project.

end

 

Project Description:

This project will install full-facility backup generators for a minimum of 32 critical facilities (estimated at 8 facilities per precinct). It will involve design, procurement, related site electrical upgrades and infrastructure, constructing and installing equipment, and fencing to protect generators. By adding backup power sources to the facilities, Harris County will ensure continued service to the residents of Harris County during power outages and provide much-needed warming centers and disaster shelters during major events. We expect to start the project by Q4 FY24 and complete by Q1 FY27.

 

Project Scope:

Key tasks involved in this project include the design and construction of equipment foundation structures, upgrading the related electrical systems to accommodate the generators, installing ATS and Direct Connect Equipment, setting equipment on foundation structures, making electrical tie-ins, trenching, running conduit, and running wiring, and supporting services, systems, and equipment needed for each site.  When the project is complete, we expect to have systems that will ensure uninterrupted power supply to the facilities, allowing continued use of the facility in the event of a power outage.  The equipment installed will provide enough electrical generation to fully operate the facilities, instantaneously upon sensing the power drop from utility suppliers. We expect to start the project by Q4 FY24 and complete the first batch of smaller facility generators completing by Q4 FY2025 with the largest generators coming online by Q4 FY2026.

 

Phase 2 will be addressed in a future investment memo. It will include additional facilities and generator installation and upgrades. The full scope of Phase 2 will be assessed by the Harris County Engineering Department (HCED) during Phase 1.

 

Justification:

By adding backup generators to the facilities, Harris County will ensure continued service to the residents of Harris County during power outages and provide much needed warming centers and disaster shelters during major events.

 

Alternatives and Engagement:

There are no known, practical alternatives for a backup power system that will provide uninterrupted power to facilities.  The only alternative is to forego investing in these systems and simply allow the facilities to be without power when the grid goes down.  Any delay in the project risks a lengthy power outage and temporary loss of ability to use the facilities the next time there is a power outage. Stakeholders are all Harris County residents and others who are served by these facilities, the employees, and other people in the general area who may not have an alternative power source during a prolonged power outage.

 

Anticipated Project Expenditures and Timeline:

Scope of Work

Estimated Cost

Estimated Completion

Phase 1 - PCT 1: Generator Installations

$8,780,000

Q4 FY2026

Phase 1 - PCT 2: Generator Installations

$8,780,000

Q4 FY2026

Phase 1 - PCT 3: Initial Generator Procurement (6/4 Investment Memo)

$1,480,000

Q4 FY2024

Phase 1 - PCT 3: Generator Installations

$7,300,000

Q4 FY2026

Phase 1 - PCT 4: Generator Installations

$8,780,000

Q4 FY2026

Staff Augmentation

$3,780,000

Q4 FY2026

Project TOTAL

$38,900,000

 

Previously Approved Authorization on 6/4/2024

$1,480,000

 

Incremental Authorization Requested

$ 37,420,000

 

Note: Contingency included in the above Estimated Costs

The $1,480,000 already transferred to Precinct 3 on 6/4/2024 Court will remain with Precinct 3 to be used on generators, with OMB to determine the appropriate CP fund to use. Future budget allocations for each precinct’s projects will be transferred to the respective precinct as needed. Engineering will notify OMB of any needed future budget allocations.

Alignment with Goal(s):

X Justice and Safety

X Economic Opportunity

_ Housing

X Public Health

_ Transportation

_ Flooding

_ Environment

X Governance and Customer Service

 

Previous Court Action:

Date

Agenda Item #

Action Taken

6/4/2024

412

Approved - Request for approval of the Final Investment Memo for the Precinct 3 Generator Procurement project for an amount of $1,478,741 and request for approval of commercial paper funding in the amount of $1,480,000.

 

Address: Multiple locations throughout Harris County.

Precinct(s): Countywide

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Commercial Paper

$

$1,480,000

$1,480,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$1,480,000

$1,480,000

$

Additional Budget Request

 

Commercial Paper

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$1,480,000

$1,480,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: August 6, 2024

Anticipated Implementation Date (if different from Court date): N/A

Legal funding compliance confirmed by: Paige Abernathy, Assistant County Attorney, 7/23/2024

Department Approval by: Ross Hosket, P.E., CFM, Env SP, Interim Director, Capital Project Facilities, Harris County Engineering Department

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 7/26/2024

 

 

Commercial Paper Request (For OMB use only):

Receiving Department: N/A

Project PeopleSoft ID: N/A

CP Series Description: N/A

OMB Financial Management contact: N/A