Legislation Details

File #: 24-7493    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/24/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of a change in contract with E.P. Brady, Ltd., in connection with Kingslake Forest Subdivision Drainage Improvements, with no change in the amount, Job No. 22/0348-1, Grant Fund, UPIN 19101MF17A01, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 100%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN - 19101MF17A01 - Job No. 22/0348

Vendor/Entity Legal Name (if applicable): E.P. Brady, Ltd.

 

MWDBE Contracted Goal (if applicable): 20%

MWDBE Current Participation (if applicable): 100%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with E.P. Brady, Ltd., in connection with Kingslake Forest Subdivision Drainage Improvements, with no change in the amount, Job No. 22/0348-1, Grant Fund, UPIN 19101MF17A01, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 100%.

end

 

Background and Discussion:

Kingslake Forest Subdivision located in Northeast Harris County, Texas, Precinct 1. Under existing conditions, the Kingslake Forest Subdivision has experienced flood damage during extreme rainfall events. The project will include storm sewer improvements along multiple streets in the neighborhood. The proposed drainage improvements will consist of removal and replacement of existing storm sewers, as well as replacement of the inlets. A detention basin will also be added to the southeastern portion of the neighborhood, to mitigate for the impacts to Greens Bayou tributary P127-00-00 from the improvements. This detention basin will be dry bottom basin, with a perimeter concrete trail. The basin may include recreational features such as trees, signage, trash receptables, and benches.

 

The Change in Contract includes the following:

 

•                     Quantity Adjustment: The addition of quantities reconciles actual quantities used in construction with the estimated quantities for completing the proposed scope of work. Items 5, 12, 22, and 89 were increased for an addition in the amount of $35,686.25. Items 1, 41, and 92 were decreased for a deduction in the amount of $35,686.25.

 

•                     The additions and deductions result in a net change in the amount of $0.00.

 

 

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Kingslake Forest subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/29/2022

22-7343

Award of Construction Contract - E.P. Brady, Ltd.

08/29/2023

23-4848

Contract Amendment

09/19/2023

23-5368

Contract Amendment (22/0348-1) for additional funds and extension of project term - Bond

12/19/2023

23-7005

Contract Amendment (22/0348-2) for additional funds and extension of project term - Bond

03/26/2024

24-1727

Contract Amendment (22/0348-3) for extension of project term - Bond

06/04/2024

24-1727

Contract Amendment (22/0348-4) for extension of project term - Bond

07/15/2024

24-4036

Contract Amendment (22/0348-5) for additional funds - Bond

 

Location: Kingslake Forest Subdivision, Houston, Texas

Address (if applicable): N/A

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: December 10, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Change in Contract (CIC)