Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0443, UPIN 22101MF2CW01
Vendor/Entity Legal Name (if applicable): Mar-Con Services, LLC
MWBE Contracted Goal (if applicable): 32%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Mar-Con Services, LLC, in connection with final construction of Miller Road 2 - Wallisville Road to US 90 - 2022, adding 267 calendar days, with an addition in the amount of $548,921.20, Job No. 23/0443-1, UPIN 22101MF2CW01, Precinct 1, MWBE Contracted Goal: 32%, MWBE Current Participation: 100%.
end
Background and Discussion:
Harris County intends to provide improvements to Miller Road 2, from Wallisville Road to US 90. The pavement is planned to be re-constructed from asphalt to concrete pavement.
Change order includes the following items:
PCO - 4 RFI#024 - Electro Quip Cost Est - (RFI - 24) $28,932.22 zero calendar days
PCO - 6 RFI#029 - Guardrail Issues (at Kimberlee Street) - (RFI - 29) $2,884.70 2 calendar days
PCO - 8 RFI#032 - 5in Slope Paving - (RFI - 32) $5,827.00 15 calendar days
PCO - 9 Final - Miller Road 2 - Wallisville Road to US 90 - 2022 $509,822.68 zero calendar days
PCO - 5 RFI#028 - Concrete Barrier - (RFI - 28) $1,454.60 zero calendar days
PCO - 7 RFI#026 - Project Delays - (RFI - 26) $0.00 250 calendar days
Expected Impact:
The unobstructed visibility easement will allow us to move forward with the proposed improvements for the intersection of Miller Road-2 and Miller Road-1 to provide more turning area for the trucks and make sure there is enough visibility for the crossing traffic.
Alternative Options:
No other options, the proposed infrastructure is needed to complete the project.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Strengthen the County’s commitment to Vision Zero principles and goals.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
02/27/2024 |
354 (24-1164) |
Contract Award |
Location:
Address (if applicable):
Precinct(s): Precinct 1
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Other 3109 |
$ |
$548,921.20 |
$548,921.20 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$548,921.20 |
$548,921.20 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$548,921.20 |
$548,921.20 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 11/19/2026
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer
Attachments (if applicable): County Auditor’s Form 1258B