File #: 26-1967    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 3/9/2026 In control: Commissioners Court
On agenda: 3/19/2026 Final action: 3/19/2026
Title: Request for approval of a Final Investment Memo for the Purchasing Warehouse Shelving Renovation project in an amount of $133,150, and request for approval of commercial paper funding in the amount of $135,000.

Primary Department: Purchasing

Primary Department Head/Elected Official: Kimberly Williams

Managing Department: Purchasing

Managing Department Head/Elected Official: Kimberly Williams

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Purchasing Warehouse Shelving Renovation

Project ID (if applicable): TBD

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $133,150

Total Estimated Project Cost: $133,150

 

Request Summary:

title

Request for approval of a Final Investment Memo for the Purchasing Warehouse Shelving Renovation project in an amount of $133,150, and request for approval of commercial paper funding in the amount of $135,000.

end

 

Project Description:

Purchase and installation of warehouse shelving units and peripherals to replace units that have been depreciated over 20 years and mitigate risk and safety concerns for staff and public.

 

 

 

 

Anticipated Project Expenditures and Timeline:

Project Scope Breakdown

Estimated Cost

Estimated Completion

Portable loading dock

 $19,810

2/11/2026

Order Picker

 $45,337

2/11/2026

Rack System

$45,792

2/11/2026

Contingency

$22,187

-

Total

$133,126

2/11/2026

 

Justification & Alternatives:

This project supports Office of the Purchasing Agent, Asset & Materials Management division’s operational, legal, and safety responsibilities by replacing warehouse shelving units that are fully depreciated and beyond useful life. Many existing units are more than 20 years old, are not anchored to the floor, and have compromised structural components with temporary field repairs. These units are used to store heavy inventory loads, creating a material safety risk to personnel, County property, and continuity of operations.

Replacement and renovation will improve inventory control, storage safety, and operational efficiency while supporting audit readiness and stewardship of County assets. The Purchasing function includes oversight of County property and inventory accountability, including transfer and redistribution of usable supplies and materials to prevent unnecessary purchases. Modernized shelving infrastructure is necessary to safely store, track, repurpose, recycle, and prepare items for redistribution or auction. Project supports Harris County Strategic Goal 5:

•                     R: Enhance disaster preparedness, response, recovery, and resiliency through safer warehouse storage and improved inventory readiness.

o                     T7: Establish a sustainable purchasing policy for County procurement through asset reuse, repurposing, recycling, and auction practices.

o                     T8: Improve reporting and measuring of County waste stream through stronger inventory tracking and disposition management.

•                     T: Reduce GHG emissions from County operations by 40% by 2030.

o                     H4: Consistently embed sustainability considerations in the project planning and design process.

By improving warehouse storage conditions and inventory handling processes, the County strengthens emergency readiness, reduces asset loss and disposal waste, and increases the ability to reuse and recover value from County property. This is a statutorily mandated operation.

Alternatives considered included continued patch repair of existing shelving and deferred replacement. These options do not adequately address structural safety concerns, anchoring deficiencies, or the ongoing risk of equipment failure underload. Deferral also increases the likelihood of injury, property damage, inventory loss, operational disruption, and higher long-term replacement costs.

Stakeholders:
The primary stakeholders are the Purchasing Division staff, all Harris County departments, and community members. Building Operations Services and Fire Marshall’s Office has been consulted to evaluate space and safety of the project scope to ensure compliance with County standards and alignment with operational needs.

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: T: Reduce GHG emissions from County operations by 40% by 2030.

Justice/Safety Initiative (Goal 1):  Choose an item.

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): Choose an item.

Health Initiative (Goal 4): Choose an item.

Climate/Resilience Initiative (Goal 5): T7: Establish a sustainable purchasing policy for County procurement.

Housing Initiative (Goal 6): Choose an item.

 

Previous Court Action:

Date

Agenda Item #

Action Taken

 

 

 

 

 

 

 

 

 

                     

Address: 601 Lockwood Drive, Houston, TX 77011

Precinct(s): Precinct 2

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$135,000

$135,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$135,000

$135,000

$

Total Funding Request

$

$135,000

$135,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 3/19/2026

Anticipated Implementation Date (if different from Court date): 3/31/2026

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, First Assistant County Attorney-Legal Operations, 3/8/2026

Department Approval by: Kimberly Williams, Purchasing Agent, Office of the Purchasing Agent, 3/10/2026

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 3/9/2026

 

Commercial Paper Request (For OMB use only):

Receiving Department: Purchasing

Project PeopleSoft ID: TBD

CP Series Description: Commercial Paper Series D-2 can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the Purchasing Warehouse Shelving Renovation project and is expected to be repaid within the next three fiscal years, either through bonds, budgetary means, or pay-as-you-go sources.

Note: Commercial Paper is issued in increments of $5,000, and any excess is not available for departmental spending.

 

OMB Financial Management contact: Fahad Gulzar, Acting Deputy Executive Director, Office of Management and Budget