Legislation Details

File #: 25-5412    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 8/18/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Request for approval of a Final Investment Memo for the Precinct 4 Katy Service Center Roof Enhancement Upgrades project for an amount of $530,000, and request for approval of commercial paper funding in the amount of $530,000.

Primary Department: Commissioner, Precinct 4

Primary Department Head/Elected Official: Commissioner, Lesley Briones

Managing Department: Commissioner, Precinct 4

Managing Department Head/Elected Official: Commissioner, Lesley Briones

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Precinct 4 Katy Service Center Roof Enhancement Upgrades

Project ID (if applicable): KATYSVC_ROOF

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $530,000

Total Estimated Project Cost: $530,000

 

Request Summary:

title

Request for approval of a Final Investment Memo for the Precinct 4 Katy Service Center Roof Enhancement Upgrades project for an amount of $530,000, and request for approval of commercial paper funding in the amount of $530,000.

end

 

Project Description:

This project at the Katy Service Center focuses on a comprehensive roof improvement aimed at enhancing energy efficiency, durability, and overall performance. This initiative includes upgrading the existing roofing system with a high-performance thermoplastic membrane, advanced insulation, and modernized drainage components. Key enhancements feature the installation of a 60 mil TPO membrane, energy-efficient insulation, a hail- and fire-resistant cover board, and new galvanized gutters and downspouts-all designed to deliver long-term resilience and improved building performance.

Anticipated Project Expenditures and Timeline: Project Breakdown

 

Unit Type

Unit Count

Unit Price

Total

Estimated Completion

MO - Forklift w/ Operator

2

$13,534

$27,068

May 2026

LF - 2x6 PT Wood Plate

1,600

$3

$4,800

May 2026

SF - 2" Polystyrene MEPS

19,500

$4

$78,000

May 2026

SF - Wind Add to MEPS

19,500

$1

$19,500

May 2026

SF - 1/2" Gypsum Board

19,500

$3

$58,500

May 2026

SF - Wind Add to Gypsum

19,500

$1

$19,500

May 2026

SQ - 60 Mil TPO Membrane

195

$444

$86,580

May 2026

SQ - Low VOC Adhesive Add

195

$93

$18,135

May 2026

LF - Drip Edge

1,600

$23

$36,800

May 2026

LF - Gutter

1,600

$28

$44,800

May 2026

LF - Gutter Kynar Finish

1,600

$10

$16,000

May 2026

LF - Downspout

700

$12

$8,400

May 2026

LF - Downspout Kynar Finish

700

$4

$2,800

May 2026

LF - Downspout 24 Gauge Add

700

$3

$2,100

May 2026

LF - Safety Line Install

1,560

$29

$45,240

May 2026

LF - Safety Line Demolition

1,560

$21

$32,760

May 2026

LF - Drip Edge Demo

1,600

$1

$1,600

May 2026

LF - Gutter Demo

1,600

$3

$4,800

May 2026

LF - Downspout Demo

700

$2

$1,400

May 2026

Contingency

 

 

$21,217

 

Total

 

 

$530,000

 

 

Justification & Alternatives:

The proposed investment is necessary to ensure the long-term protection of Precinct 4’s fleet and facility assets. The new roof system includes:

•                     Energy efficiency through a high-reflective, 60 mil TPO membrane compliant with City of Houston standards.

•                     Enhanced insulation to R-11.2, reducing future cooling and heating costs.

•                     A ½" Securock gypsum cover board, providing improved hail and fire resistance.

•                     A 20-year manufacturer warranty, minimizing lifecycle maintenance costs.

•                     New 24-gauge prefinished gutters and downspouts for improved drainage and corrosion resistance

 

The project enhances resilience, energy performance, and visual integrity of the facility while aligning with long-term infrastructure stewardship goals.

Maintaining the current roofing system is not viable. The existing roof shows signs of degradation that, if left unaddressed, may lead to leaks, higher HVAC usage, and damage to building interiors and operational assets. Temporary patching is not cost-effective over time. Prior repair efforts have proven insufficient to extend the lifespan of the existing roof. A full tear-down and rebuild is not cost-effective and would exceed current budget allocations. Instead, employing more modern materials and energy-efficient solutions is recommended to meet and exceed warranty and performance standards.

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A Choose an item.

Justice/Safety Initiative (Goal 1):   Choose an item.

Infrastructure Initiative (Goal 2):  Choose an item.

Economy Initiative (Goal 3): Choose an item.

Health Initiative (Goal 4): Choose an item.

Climate/Resilience Initiative (Goal 5): Choose an item.

Housing Initiative (Goal 6): Choose an item.

Decision Analysis Matrix Score (rubric on last page): N/A

 

 

Previous Court Action:

Date

Agenda Item #

Action Taken

 

 

 

 

 

 

 

 

 

 

Address: 16635 Clay Road, Houston, TX 77084

Precinct(s): Precinct 4

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$530,000

$530,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$530,000

$530,000

$

Total Funding Request

$

$530,000

$530,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/26/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, Special Assistant County Attorney, 8/14/2025

Department Approval by: Jonathan Castrejon, Director of Finance, June 29th, 2025

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 8/15/2025

Commercial Paper Request (For OMB use only):

Receiving Department: Commissioner, Precinct 4

Project PeopleSoft ID: KATYSVC_ROOF

CP Series Description: Commercial Paper Series D-3 can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the Precinct 4 Katy Service Center Roof Enhancement Upgrades project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.

Note: Commercial Paper is issued in increments of $5,000 and the excess is not available to be spent by the department

OMB Financial Management contact: Amy Perez, Deputy Executive Director, Office of Management and Budget