Title: Request for approval of change order 31 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,804,195.25 to $24,805,422.18.
Attachments: 1. HAY Center CIC 7 Backup Documents

Primary Department: Housing and Community Development

Primary Department Head/Elected Official: Thao Costis, Executive Director

 

Secondary Department: County Engineer

Secondary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): D2017-088; HAY Center Campus

Vendor/Entity Legal Name (if applicable): Arch-Con Corporation

 

MWBE Contracted Goal (if applicable): 35%

MWBE Current Participation (if applicable):

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of change order 31 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,804,195.25 to $24,805,422.18.

end

 

Background and Discussion:

This project includes new construction of two buildings and site development on a 3.268-acre site at 3131 Gulf Freeway.  The residential building is a three story 50-unit building for youth aging out of foster care with community space, kitchen, a small gym, a business center, and private study rooms.  The other building is a one-story commercial building for wrap-around services, including huddle/meeting rooms, a computer lab, life skills training rooms, administrative offices, administrative and building support.  The two buildings are connected by a covered walkway. Site development includes underground detention below surface parking and outdoor landscaped areas.

 

Expected Impact:

Changes allow the completion of the project in accordance with the original intent of the project. Changes include increasing the construction contract from $24,804,195.25 to $24,805,422.18.  This request will be funded by the already approved 2017 CDBG-DR funds for the residential building portion and treasury ARPA funds for the services building portion.

 

Alternative Options:

Commissioners court could delay approval, not allowing the project to be completed as intended.

 

County Strategic Plan Goal:  6. Help residents achieve housing stability.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): W2: Increase stock of permanent supportive housing.

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/13/2022

P.47 395

[Purchasing] Request for approval of an award on the basis of only bid to Arch-Con Corporation in the amount of $23,356,200 for construction for a new service and residential buildings at the HAY Center Foundation in Precinct 1, and for the County Clerk to execute any applicable bonds to be received (220335), MWDBE Contracted Goal: 35%

9/19/2023

#20

[Community Services Department] Request for approval of change orders 1, 2, 3, and 4 for the HAY Center Project and to increase the construction contract with ARCH-Con Corporation from $23,356,200 to $23,879,532.01.

1/30/2024

#25

[Housing and Community Development] Request for approval of change orders 5,6,7,8,9,10,11,12,12,14 and 15 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $23,879,532.01 to $24,050,607.34, MWDBE Contracted Goal: 35%.

8/27/2024

p.19; 173

[Housing and Community Development]  Request for approval of change orders 16, 17, 18, 19, 20, 21, 22 and 23 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,050,607.34 to $24,182,716.04, MWDBE Contracted Goal: 35%.

8/27/2024

p.19; 174

[Housing and Community Development]  Request for approval of change orders 24, 25, 26, 27, and 28 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,182,716.04 to $24,230,610.76.

11/12/2024

p.17; 148

Request for approval of change order 29 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,230,610.76 to $24,305,044.95, adding 48 calendar days, MWDBE Contracted Goal: 35%.

11/12/2024

p.17; 149

Request for approval of change order 30 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,305,044.95 to $25,680,166.94, adding 42 calendar days, MWDBE Contracted Goal: 35%

 

Location:

Address (if applicable): 3131 Gulf Freeway, Houston, Texas 77003

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Affordable Rental Housing

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other

$

$1,226.93

$1,226.93

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$1,226.93

$1,226.93

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$1,226.93

$1,226.93

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 3/27/2025

 

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Sam Borders, Director, Multi- Family Housing Development, Harris County Housing & Community Development

 

Attachments (if applicable):  Change Orders: 31 (PCO 26): PCP-36, PCP-48, PCP-49, PCP-50