Legislation Details

File #: 26-6070    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 9/3/2026 In control: Commissioners Court
On agenda: 9/17/2026 Final action:
Title: Request for approval to execute an agreement with Transcend Engineers & Planners, LLC in the amount of $106,041.00 for professional engineering services in connection with a new traffic signal with pedestrian related appurtenances at the intersection of Grissom Road at Bay Area Boulevard – 2026, UPIN 26035HF7VV01, Precinct 2, MWBE Contracted Goal: 19.967%.
Sponsors: Mony Hossain
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: Commissioner, Precinct 2

Secondary Department Head/Elected Official: Adrian Garcia, Commissioner

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN - 26035HF7VV01

Vendor/Entity Legal Name (if applicable): Transcend Engineers & Planners, LLC

 

MWBE Contracted Goal (if applicable): 19.967%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Transcend Engineers & Planners, LLC in the amount of $106,041.00 for professional engineering services in connection with a new traffic signal with pedestrian related appurtenances at the intersection of Grissom Road at Bay Area Boulevard - 2026, UPIN 26035HF7VV01, Precinct 2, MWBE Contracted Goal: 19.967%.

end

 

Background and Discussion:

Traffic signals are constructed to improve the operation of an intersection and better facilitate pedestrian activities. As such, the consultant will be tasked with the signal design of the intersection and an evaluation of left turn storage to improve operations. The consultant will also be tasked with evaluating pedestrian accessibility through the provision of crosswalks and associated median nose opening adjustments required to facilitate pedestrian activities.

 

Expected Impact:

Designing and building a traffic signal at this intersection will improve operations and better facilitate pedestrian activities.

 

Alternative Options:

An alternative is to not build a signal at the intersection, which will not provide up to date operations and pedestrian benefits.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

1/09/2025

376; 25-0414

Request by the Office of the Purchasing Agent for approval on the basis of highest overall evaluations with multiple vendors for professional architectural and/or engineering services to provide design services for the development and implementation of various roadway & mobility infrastructure projects for the Office of the County Engineer (240334).

 

Location:

Address (if applicable): Grissom Road at Bay Area Boulevard

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$106,041.00

$106,041.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$106,041.00

$106,041.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$106,041.00

$106,041.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 9/17/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Dr. F. Mike Etienne, Chief of Planning and Development Services, Office of the County Engineer

 

Attachments (if applicable): Professional Services Agreement