File #: 25-4379    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/1/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval of a change in contract with First Class Units, Inc., in connection with final construction of Community Monuments PCT 2 - 2021, adding 13 calendar days, with a deduction in the amount of $46,508.25, Job No. 22/0014-3, UPIN 21102MF23901, Precinct 2, MWBE Contracted Goal: 17%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0014, UPIN 21102MF23901

Vendor/Entity Legal Name (if applicable): First Class Units, Inc.

 

MWBE Contracted Goal (if applicable): 17%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with First Class Units, Inc., in connection with final construction of Community Monuments PCT 2 - 2021, adding 13 calendar days, with a deduction in the amount of $46,508.25, Job No. 22/0014-3, UPIN 21102MF23901, Precinct 2, MWBE Contracted Goal: 17%.

end

 

Background and Discussion:

The project involves constructing four monuments on Precinct 2 road medians-two in Channelview (510 Sheldon Road and 14807 Woodforest Boulevard) and two in North Shore (514 Normandy Street and 16 Uvalde Road).

This change in contract includes:

PCO#6: In response to a community request, the monument originally planned for installation in the third median at Channelview was proposed to be relocated to the second median. This change required additional coordination and review to ensure safety and compliance with sight distance requirements. Specifically, the designer and Traffic Group needed to evaluate the proposed location to confirm that the monument would not create any sight obstruction issues. This process included design verification, field review, and staking of the new location. As a result, the contractor experienced a delay of 13 calendar days while awaiting completion of this review and the subsequent approval to proceed. - $0.00 - 13 days

PCO#7:  This change in contract includes the final reconciliation of actual quantities used in construction against the bid quantities. -$46,508.25

 

 

 

Expected Impact:

This action allows for accommodating the owner request and enhance visibility of monuments. 

 

Alternative Options:

Continue with the original plan.

 

County Strategic Plan Goal:  3. Make our economy more inclusive.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): K2: Partner with community organizations to create new and build upon existing apprenticeship opportunities,

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

03/26/2024

404 (24-1880)

Contract Award

01/23/2025

58 (25-0585)

Contract Amendment #1 for additional funds and extension of project term

03/27/2025

87 (25-1462)

Contract Amendment #2 for additional funds and extension of project term

05/08/2025

389 (25-2744)

Substantial Completion

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109, 3249

$

-$46,508.25

-$46,508.25

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$46,508.25

-$46,508.25

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$46,508.25

-$46,508.25

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/7/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B