Harris County Logo
File #: 24-0937    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 2/13/2024 In control: Commissioners Court
On agenda: 2/27/2024 Final action: 2/27/2024
Title: Request for approval of change in contract No. 2 with Lecon, Inc., for the Keegans Bayou- General Repairs - US 59 to South Dairy Ashford Road, adding 43 calendar days and resulting in an addition of $749,600.83 to the contract amount. (Brays Bayou Watershed, Project ID D118-00-00-X009, Job No. 22/0091, Precinct 4, MWDBE Contracted Goal: 27.85%, MWDBE Current Participation: 28.50%).

Department: Flood Control District

Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): D118-00-00-X009

Vendor/Entity Legal Name (if applicable): Lecon, Inc.

 

MWDBE Contracted Goal (if applicable): 27.85%

MWDBE Current Participation (if applicable): 28.50%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of change in contract No. 2 with Lecon, Inc., for the Keegans Bayou- General Repairs - US 59 to South Dairy Ashford Road, adding 43 calendar days and resulting in an addition of $749,600.83 to the contract amount. (Brays Bayou Watershed, Project ID D118-00-00-X009, Job No. 22/0091, Precinct 4, MWDBE Contracted Goal: 27.85%, MWDBE Current Participation: 28.50%).

end

 

Background and Discussion:

Additional Traffic Control Plan devices were needed to enhance pedestrian safety and trail closure during excavation of outfall structures and during the night when the contractor is not on site. A new bid item will be added to reduce the use Riprap Gradation 1 due to the market shortage of concrete Riprap. An additional 43 inclement weather days were added to the contract.

 

Expected Impact:

This change in contract is needed in order to complete the construction contract for this project.

 

Alternative Options:

This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/14/2022

205.

Award

06/27/2023

125.

Change in Contract No. 1

 

Location:

Address (if applicable):

Precinct(s): Choose an item.

 

Fiscal and Personnel Summary

Service Name

Choose an item.

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Tax Revenue - FCD

$

$749,600.83

$749,600.83

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$749,600.83

$749,600.83

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$749,600.83

$749,600.83

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: February 27, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Change in Contract and Map