Legislation Details

File #: 24-5080    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/13/2024 In control: Commissioners Court
On agenda: 8/27/2024 Final action: 8/27/2024
Title: Request for approval of a change in contract with Serco Construction Group, Ltd., in connection with Cedar Bayou Park East and West Subdivision Drainage Improvements, with an addition in the amount of $14,967.86, Job No. 23/0042-2, UPIN 19102MF15W01, Precinct 2, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 100%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0042 - UPIN 19102MF15W01

Vendor/Entity Legal Name (if applicable): Serco Construction Group, Ltd.

 

MWDBE Contracted Goal (if applicable): 26%

MWDBE Current Participation (if applicable): 100%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Serco Construction Group, Ltd., in connection with Cedar Bayou Park East and West Subdivision Drainage Improvements, with an addition in the amount of $14,967.86, Job No. 23/0042-2, UPIN 19102MF15W01, Precinct 2, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 100%.

end

 

Background and Discussion:

The Cedar Bayou Park East and West Subdivision Drainage Improvements project site consists of subdivision drainage improvements and stormwater detention basin located south of IH 10 from Sjolander Road to Bayou

Boulevard, in east Harris County; discharging into HCFCD Channels Q113-00-00 and Q114-00-00. Major work

activities include approximately 25,300 linear feet of reinforced concrete storm sewer consisting of various reinforced concrete pipe sizes, reinforced concrete box sizes, inlets, manholes, junction boxes, culvert headwall/wingwall structures, removal and reconstruction of existing driveways and proposed detention pond.

 

The Change in contract request includes added quantities for the following:

 

Quantity Overruns - Added (1 Each) to Item No. 11 - Remove Existing Wooden Pedestrian Bridges with an additional cost of $5,470.00, added (24 Linear Feet) to Item No. 71 - 24-Inch Corrugated Metal Pipe with an additional cost of $1,802.40, added (18 Square Yards) to Item No. 76 - Geotextiles For All Weather Access Road with an additional cost of $92.70, added (25.42 Square Yards) to Item No. 82 - Concrete Pilot Channel (5 inches) with an additional cost of $3,152.08, and added (94.50 Linear Feet) to Item No. 130 - Dense-Graded Hot-Mix Asphalt Surface Course with an additional cost of $4,450.68. The addition of $14,967.86 reconciles actual quantities used in construction with the estimated quantities for completing the proposed scope of work.

 

 

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Cedar Bayou Park East and West Subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the original scope of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/04/2023

23-1874

Contract Award

04/23/2024

24-2218

Contract Amendment (23/0042-1) for additional funds

 

Location: Cedar Bayou Park East and West Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

$14,967.86

$14,967.86

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$14,967.86

$14,967.86

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$14,967.86

$14,967.86

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: August 27, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Change in Contract (CIC)