File #: 25-5406    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 8/18/2025 In control: Commissioners Court
On agenda: 8/26/2025 Final action: 8/26/2025
Title: Request for approval of a Final Investment Memo for the Precinct 4 Tomball Print Shop Project, for an amount of $65,000 and a request for approval of commercial paper funding in the amount of $65,000.

Primary Department: Commissioner, Precinct 4

Primary Department Head/Elected Official: Commissioner Lesley Briones

Managing Department: Commissioner, Precinct 4

Managing Department Head/Elected Official: Commissioner Lesley Briones

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: Precinct 4 Tomball Sign Shop

Project ID (if applicable): TSC_SIGNSHOP

Vendor Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Incremental Authorization Requested: $65,000

Total Estimated Project Cost: $65,000

 

Request Summary:

title

Request for approval of a Final Investment Memo for the Precinct 4 Tomball Print Shop Project, for an amount of $65,000 and a request for approval of commercial paper funding in the amount of $65,000.

end

Project Description:

This project involves a full upgrade of aging hardware in the Sign Shop, which serves as the central production hub for all road signage, internal banners, and paper-based signage for the organization. The upgrade includes the purchase and installation of new commercial-grade plotters, wide-format printers, precision cutters, and a modern rollover table. This new suite of equipment will replace outdated and inefficient machines that are no longer meeting production demands. The goal is to improve output speed, enhance signage quality, and reduce manual labor for the Sign Shop team.

                     

Anticipated Project Expenditures and Timeline:

Unit Type

Unit Count

Unit Price

Total

Estimated Completion

HP L730W 64" LATEX PRINTER W/WHITE with install

1

$25,265

$25,265

March 2026

HP DesignJet Z6 44" PostScript® Printer

1

$4,995

$4,995

March 2026

55"x113" Rollover Flexi Height Table & Accessories

1

$18,180

$18,180

March 2026

Rollover Table Shipping

1

$1,950

$1,950

March 2026

Summa-S3TC160 62” S-Class 3 Series

1

$11,395

$11,395

March 2026

Contingency

 

 

$3,215

 

Total

 

 

$65,000

 

 

Justification & Alternatives:

The current hardware in the Sign Shop has exceeded its useful life expectancy, resulting in slower production times, lower-quality outputs, and increased maintenance issues. With the demand for both road and internal signage steadily increasing due to expanded operations, a modernized equipment suite is critical. Upgrading to newer, faster, and more precise equipment will enable the team to meet turnaround expectations while improving the durability and clarity of the signs produced. The inclusion of a new rollover table will significantly streamline the process of applying signage to metal and cardboard backings, which is currently labor-intensive and time-consuming. These improvements will directly impact operational efficiency, reduce downtime, and support our branding and public safety efforts across the precinct.

One alternative is to continue operating with the current hardware until individual components fail beyond repair. However, this reactive approach would lead to unpredictable delays in production, reduced quality, and increased maintenance costs. Another option would be to selectively replace only the most critical pieces of equipment, but this would not resolve systemic bottlenecks or eliminate inefficiencies in the overall workflow. Outsourcing signage production was also considered but ultimately dismissed due to higher long-term costs, reduced control over quality and turnaround, and security concerns related to sensitive or time-bound signage (e.g., road safety updates or emergency notices). The full hardware refresh provides the most sustainable and cost-effective path forward.

Anticipated Impact on Other Funds (If Applicable):

Fund Code

Description

Estimated Cost

Funding Method  (Existing or Future Budget Request Required)

Estimated Date of Needs

 

 

$-

 

-

 

 

$-

 

-

Total

 

$-

 

-

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):   Choose an item.

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): Choose an item.

Health Initiative (Goal 4): Choose an item.

Climate/Resilience Initiative (Goal 5): Choose an item.

Housing Initiative (Goal 6): Choose an item.


Decision Analysis Matrix Score (rubric on last page):

Previous Court Action:

 

Date

Agenda Item #

Action Taken

 

 

 

 

 

 

 

 

 

 

Address: 6600 Bissonnet St, Houston, TX 77074

Precinct(s): Precinct 4

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

$

$65,000

$65,000

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$65,000

$65,000

$

Total Funding Request

$

$65,000

$65,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/26/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

Legal funding compliance confirmed by: Paige Abernathy, Special Assistant County Attorney, 8/14/2025

Department Approval by: Jonathan Castrejon, Director of Finance, July 29th, 2025

OMB CIP Team Approval by: William McGuinness, Director-Capital Projects & Infrastructure, 8/15/2025

________________________________________

Commercial Paper Request (For OMB use only):

Receiving Department: Commissioner, Precinct 4

Project PeopleSoft ID: TSC_SIGNSHOP

CP Series Description: Commercial Paper Series D-3 can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the Precinct 4 Tomball Sign Shop Hardware Upgrades project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources. OMB Financial Management contact: Amy Perez, Deputy Executive Director, Office of Management and Budget