Title: Request for approval of a change in contract with Texas Wall & Landscape, LLC in connection with construction of Townsen Park-n-Ride Multimodal Connector, adding 9 calendar days, with an addition in the amount of $22,973.96, Job No. 23/0268-2, UPIN 14104MF0AV01, Precinct 3, MWBE Contracted Goal: 3%.

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0268, UPIN 14104MF0AV01

Vendor/Entity Legal Name (if applicable): Texas Wall & Landscape, LLC

 

MWBE Contracted Goal (if applicable): 3%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Texas Wall & Landscape, LLC in connection with construction of Townsen Park-n-Ride Multimodal Connector, adding 9 calendar days, with an addition in the amount of $22,973.96, Job No. 23/0268-2, UPIN 14104MF0AV01, Precinct 3, MWBE Contracted Goal: 3%.

end

 

Background and Discussion:

The project consists of construction of multimodal connector trail that will connect Spring Creek Greenway Hike and Bike trail to Townsen Park and Ride as well as to the historical US 59 bridge crossing the San Jacinto River in Harris County Precinct 3


This change in contracts includes:

                     Change includes cost and time for installation of seal slab underneath the channel lining ($17,325.00 - 5 days).

                     Cost of adding bid item for trench safety system. ($4220.00 - 3 days). 

                     Cost and time for removal of additional abandoned Reinforced concrete pipe and Manhole in conflict with proposed work. ($1,428.96 - 1 day).

 

Expected Impact:

Change allows to install seal slab underneath the channel lining per TXDOT detail, allows to add trench safety system to the project per standard detail and remove additional abandoned structure which conflicted with proposed work.

 

Alternative Options:

to re design the work which would be costly.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/19/2023

272 (23-7429)

Contract Award

10/29/2024

39 (24-6552)

Contract Amendment #1 for additional funds and extension of project term

 

Location:

Address (if applicable): Townsen Park and Ride

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$22,973.96

$22,973.96

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$22,973.96

$22,973.96

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$22,973.96

$22,973.96,

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 4/10/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architecture Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B