Legislation Details

File #: 26-5744    Version: 1 Name:
Type: Contract - Amendment Status: Agenda Ready
File created: 8/31/2026 In control: Commissioners Court
On agenda: 9/17/2026 Final action:
Title: Request for approval of a change in contract with FMG Construction Group, LLC., in connection with 28511 Old Washington Rd (Hockley Service Center) - Renovation - 2022, adding 5 calendar days, with an addition in the amount of $7,789.42, Job No. 24/0392, UPIN 22035MF2HE01, Precinct 4, MWBE Contracted Goal: 15%, MWBE Current Participation: 97.69%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP County

 

Secondary Department: Commissioner, Precinct 4

Secondary Department Head/Elected Official: Alice Lee/Commissioner Briones

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 24/0392 - 22035MF2HE01

Vendor/Entity Legal Name (if applicable): FMG Construction Group LLC

 

MWBE Contracted Goal (if applicable): 15%

MWBE Current Participation (if applicable): 97.69%

Justification for 0% MWBE Participation Goal:  Choose an item.

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with FMG Construction Group, LLC., in connection with 28511 Old Washington Rd (Hockley Service Center) - Renovation - 2022, adding 5 calendar days, with an addition in the amount of $7,789.42, Job No. 24/0392, UPIN 22035MF2HE01, Precinct 4, MWBE Contracted Goal: 15%, MWBE Current Participation: 97.69%.

end

 

Background and Discussion:

The Interior remodel of the Hockley Service Center administration building; enclosing 1 open storage bay; New paint, flooring, and ceiling throughout; upgrading all lighting to LED; upgrading existing restrooms and add showers; modify existing main entrance.

 

Expected Impact:

Project will make facility more responsive ready with upgrading existing restrooms and add showers; modify existing main entrance.

 

Alternative Options:

Should we not move forward with this court action general contractor will not comply with Engineer on Record updated design, causing delays or project will not move forward.

 

 

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/15/2022

310

Transmittal by the Office of the Purchasing Agent of a project scheduled for advertisement for renovation and expansion of the Hockley Service Center for Harris County Precinct 4 (220388).

01/10/2023

219

Request for approval to reject the bids received for renovation and expansion of the Hockley Service Center in Precinct 4, and that the project be readvertised (220388).

12/10/2024

312

Request for approval of a project scheduled for advertisement for renovation of the Hockley Service Center for the Office of the County Engineer (240392).

2/6/2025

256

FMG Construction Group, LLC received the highest overall evaluation score and is considered the best proposal due to experience, project methodology, and completed projects of similar scope.

6/26/2025

51

Request for approval of a change in contract with FMG Construction Group, LLC. in connection with Precinct Four 28511 Old Washington Rd (Hockley Service Center) - Renovation - 2022, with an addition in the amount of $17,408.70, Job No. 24/0392, UPIN 22035MF2HE01, Precinct 4.

10/30/2025

74

Request for approval of a change in contract with FMG Construction Group, LLC, in connection with 28511 Old Washington Rd (Hockley Service Center) - Renovation - 2022, adding 7 calendar days, with an addition in the amount of $31,042.82, Job No. 24/0392, UPIN 22035MF2HE01, Precinct 4, MWBE Contracted Goal: 15%, MWBE Current Participation: 96.27%.

05/14/2026

28

Request for approval of a change in contract with FMG Construction Group, LLC. in connection with Precinct Four 28511 Old Washington Rd (Hockley Service Center) - Renovation - 2022, with an addition in the amount of $15,408.83 Job No. 24/0392, UPIN 22035MF2HE01, Precinct 4, MWDBE Contracted Goal: 15%. MWDBE Current Participation: 97.69%.

 

 

 

Location:

Address (if applicable): 28511 Old Washington Rd Hockley, TX 77447

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$7789.42

$7789.42

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$7789.42

$7789.42

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$7789.42

$7789.42

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 9/17/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Andreas Peeples, Director-Facilities Engineering and Construction

 

Attachments (if applicable):