Title: Request for approval to advertise for construction bids for Grand Parkway frontage road extension between Cumberland Ridge and Schiel Road (25/0235) (Precinct 3, MWBE Contracted Goal: 28.10%).

Primary Department: Toll Road Authority

Primary Department Head/Elected Official: Roberto Treviño, P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Proposals/Bids

 

Project ID (if applicable): 19-0901-R; CSJ: 3510-06-028; Job No.: 25/0235

Vendor/Entity Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): 28.10%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to advertise for construction bids for Grand Parkway frontage road extension between Cumberland Ridge and Schiel Road (25/0235) (Precinct 3, MWBE Contracted Goal: 28.10%).

end

 

Background and Discussion:

Based on the 2009 Market Valuation Waiver Agreement (MVWA) between TxDOT and the seven counties traversed by the Grand Parkway Project as well as the GPTC Frontage Road Policy, TxDOT or the GPTC will only be able to implement additional frontage roads once the minimum project scope is completed as identified in the MVWA.  Any modification to the MVWA requires agreement by TxDOT and all seven counties.  Additional frontage roads are able to be implemented by others as long as the additional scope does not negatively impact revenues derived from Grand Parkway.

 

September 28, 2022 Commissioners Court approved the execution of the Interlocal Agreement (ILA) with Texas Department of Transportation (TxDOT) and the Grand Parkway Transportation Corporation (GPTC).  The executed ILA with TxDOT and GPTC establish roles and responsibilities for the design, construction and maintenance of the frontage roads.  Per the terms of the ILA, HCTRA will design and construct the extension of the frontage roads, and TxDOT will review and approve design plans, as well as maintain the constructed frontage roads.     

 

When complete, the new frontage roads will provide direct access from Schiel Road to the Grand Parkway and US 290, eliminating heavy truck traffic from Schiel Road businesses from driving through the adjacent neighborhood, normally on a street with an elementary school.  This project will improve the safety of the neighborhood.  In addition, the completed frontage road will connect with Harris County’s improvements of Schiel Road intersection, which replaces the existing 2-lane asphalt road with a 4-lane concrete boulevard.  TxDOT will maintain this section of the roadway when the project has been completed.

 

Expected Impact:

Project will allow businesses along Schiel direct access to Grand Parkway, removing the need to travel through adjacent neighborhoods. 

 

Alternative Options:

No other recommended solutions for this identified need.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/3/2019

3.a.4

Approval of an ESA for Surveying services

12/3/2019

3.a.5

Approval of an ESA for Design services

4/27/2021

101

Approval of an ESA for Environmental and Communications Services

9/28/2021

262

Approval of a Final Investment Memo

9/28/2021

263

Approval of an ILA with TxDOT and the GPTC

4/26/2022

109

Approval a revised ILA with TxDOT and the GPTC

 

Location:

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering & Construction Services

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Revenue - TRA

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/7/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority

 