Title: Transmittal by the Toll Road Authority of the completed Harris County Freight Study Report (Countywide).
Attachments: 1. 26-6675 - HCTRA_TruckRouteStudy_ExecutiveSummary-FINAL
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: Toll Road Authority

Primary Department Head/Elected Official:  Roberto Treviño, P.E., Executive Director

 

Secondary Department: County Engineer

Secondary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

 

Project ID (if applicable): N/A

Vendor/Entity Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Transmittal by the Toll Road Authority of the completed Harris County Freight Study Report (Countywide).

end

 

Background and Discussion:

On March 14, 2023, Commissioner’s Court directed both the Harris County Engineering Department and the Harris County Toll Road Authority to update the Harris County Truck Route Study to determine the future freight needs of the county and identify investment opportunities that will ensure the safe and efficient movement of goods/services in the region while improving the quality of life for Harris County residents. The study should also determine possible alignments with the Texas Delivers 2050 Freight Plan.

 

On April 23, 2024, Commissioner’s Court approved the execution of an agreement with HDR Engineering, Inc., to provide professional engineering services for the update to the Harris County Truck Route Study/Freight Corridors Plan.

 

The Study began in May of 2024 and makes recommendations for freight-related projects along Harris County roadways, including planning-level cost estimates. The Study also recommends potential policy updates that would support future movement of goods and services in the region. The Steering Committee, including members from the Office of the County Engineer, all Harris County Precincts, and the Harris County Judge’s Office, were involved in the creation of the Study. Additionally, the Study takes into consideration the previous freight planning efforts of not only Texas Delivers 2050 Freight Plan, but also the previous Harris County Truck Route Study, the TxDOT Houston Freight Mobility Plan, the TxDOT Houston Regional Express Access Lanes Plan, the H-GAC Regional Goods Movement Plan, the City of Houston Truck Route Plan, the Texas State Rail Plan, the Houston-Beaumont Region Freight Rail Study, and the H-GAC Ports Area Mobility Study.

 

Recommendations from the study and pertinent data would be transferred to the Harris County Office of the County Engineer to be incorporated into the ongoing Harris County Transportation Master Plan.

 

Expected Impact:

No additional funding is expected for this request.

 

Alternative Options:

No other recommended solution for this identified need.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  G2: Implement designated corridors (e.g., HOV, BRT, truck lanes) in road design.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

3/14/2023

326

Court directive to HCTRA & OCE to complete a Freight Study and update the HC Truck Route Study

5/16/2023

158

Court approval to advertise

10/31/2023

164

Court approval to negotiate agreement with HDR

4/23/2024

198

Court approval to execute agreement with HDR

 

Location:

Address (if applicable): N/A

Precinct(s): Countywide

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 10/15/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority

 

Attachments (if applicable): Harris County Freight Study Final Report