Legislation Details

File #: 26-1218    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 2/11/2026 In control: Commissioners Court
On agenda: 2/26/2026 Final action: 2/26/2026
Title: Request for approval of a change in contract No. 5 with Allgood Construction Company, Inc., for the White Oak Bayou Federal Flood Damage Reduction Project, adding 41 calendar days (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E007, Job No. 23/0115, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 11.25%).
Attachments: 1. 022626 CIC E100-E007 PCT 1 backup.pdf

Primary Department: Flood Control District

Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): E100-00-00-E007

Vendor/Entity Legal Name (if applicable): Allgood Construction Company, Inc.

 

MWBE Contracted Goal (if applicable): 26%

MWBE Current Participation (if applicable): 11.25%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract No. 5 with Allgood Construction Company, Inc., for the White Oak Bayou Federal Flood Damage Reduction Project, adding 41 calendar days (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E007, Job No. 23/0115, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 11.25%).

end

 

Background and Discussion:

This change in contract is needed to complete the construction contract for this project. Federal Flood Control Project Channel Modifications Discrete Segment 104 White Oak Bayou Cole Creek to Hollister Street includes the installation of approximately 1.65 miles of 10‐foot to 12‐foot width concrete sidewalk bike trails, concrete sidewalk pedestrian access paths and wheelchair ramps, and excavation and re-grading approximately 4.65 miles of drainage channel, including installation of backslope swales. The purpose of this contract change is to increase the quantities of several pay items that have exceeded current contract amounts, add new pay items needed to complete the work, and reduce quantities for items that are no longer required. The contract change includes 41 Calendar Days and no increase to the budget.

 

 

Expected Impact:

This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:

This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract, which is not recommended as doing so would substantially delay the remaining work in the construction contract.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06/06/2023

240.

Contract Award

10/31/2023

151.

Change in Contract No. 1

01/23/2025

74.

Change in Contract No. 2

05/22/2025

98.

Change in Contract No. 3

10/16/2025

151.

Change in Contract No. 4

 

Location: N/A

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

N/A

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 2/26/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Change in Contract and Map