Title: Request for approval to execute a Utility Adjustment Agreement with Kinder Morgan Texas Pipeline, LLC in the amount of $2,378,052.00 to relocate utilities in connection with Roland Road and Related Infrastructure Drainage Improvements - 2018, UPIN 19103MF14C01, Precinct 4.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

 

Project ID (if applicable): UPIN 19103MF14C01

Vendor/Entity Legal Name (if applicable): Kinder Morgan Texas Pipeline LLC

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute a Utility Adjustment Agreement with Kinder Morgan Texas Pipeline, LLC in the amount of $2,378,052.00 to relocate utilities in connection with Roland Road and Related Infrastructure Drainage Improvements - 2018, UPIN 19103MF14C01, Precinct 4.

end

 

Background and Discussion:

The project is located within the South Mayde Creek Watershed in western Harris County. The Roland Road subdivision consists of mainly roadside ditches and has been subjected to several flooding events. The scope and proposed improvements include surface collection, ditch grading and storm sewer conveyance of the drainage along Roland Road. The existing HCFCD U201-09-00 channel will be extended from Porter Road to Katy Hockley Cutoff Road to provide reduction in inundation of the subdivision. This Utility Adjustment Agreement allows the project to move forward with the improvements by relocating the pipeline facilities that are in conflict with the proposed improvements.

 

Expected Impact:

This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This agreement is a step in the process to reduce the financial, physical, and emotional burden flood damage places on homeowners and will reduce the financial impact of recovery costs to the Roland Road and Related Infrastructure project area and surrounding homeowners, Harris County, and FEMA. The fiscal impact for this project will come from the 1070 mobility funds with the long-term goal of reducing drainage costs in the future. No impact to project schedule or staffing anticipated. This agreement allows for pipeline to be reimbursed for their relocation within their restricted timeframe of shutting down their pipeline at this project’s location.

 

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the project area will continue to experience flood risk.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

N/A

N/A

N/A

 

Location: Roland Road and surrounding area.

Address (if applicable): N/A

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109

$

$2,378,052.00

$2,378,052.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$2,378,052.00

$2,378,052.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$2,378,052.00

$2,378,052.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/22/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Harris County Engineering Department

 