Title: Request for approval of an award on the basis of low bid to A Morfin Trucking LLC in the amount of $3,126,626 for construction of the Yale Stormwater Detention Basin for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (240350), MWDBE Contracted Goal: 13.35%.

Department: Purchasing

Department Head/Elected Official: Paige McInnis

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 240350

Vendor/Entity Legal Name (if applicable): A Morfin Trucking LLC

 

MWDBE Contracted Goal (if applicable): 13.35%

MWDBE Current Participation (if applicable):

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of an award on the basis of low bid to A Morfin Trucking LLC in the amount of $3,126,626 for construction of the Yale Stormwater Detention Basin for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (240350), MWDBE Contracted Goal: 13.35%.

end

 

Background and Discussion:

This project is part of the Little White Oak Bayou Sub-Watershed Flood Risk Reduction Study completed on August 31, 2022. The feasibility study provided substantial information to forego the Preliminary Engineering Design stage and to move forward with establishing a Conceptual Design Report (CDR) and Final Design. The Hydrologic and Hydraulic (H&H) studies on multiple alternatives were not necessary, and the Precinct and Landscape Architect were coordinated with early on to generate a rendering. B2Z Engineering, Inc. is the designated design consulting firm for this project.

 

The Yale Storm Water Detention Basin (SWDB) is an interim project to mitigate future channel improvements along the existing Little White Oak Bayou (E101-00-00). The project consists of design and construction on Harris County Flood Control District (Flood Control District) property, within Precinct 2 and within City of Houston (COH) limits. The Yale SWDB is located just west of the I-45 and East Tidwell Road intersection within the White Oak Bayou Watershed (See Exhibits 1 and 2 attached). This project, along with future improvement projects, will help remove the 500-year area of inundation from an estimated 2,815 structures, 2,520 acres of land and 82.8 miles of roadway. The prioritization framework score for this project is __5.3____ and occurs in the 2nd quartile under the 2022 Prioritization Framework approved by Commissioners Court.

 

 

 

 

 

Expected Impact:

The objective of this project is to enhance stormwater quality to the Clear Creek Channel, HCFCD Unit E101-00-00.

 

Alternative Options:

There is no alternative option for this project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

X Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08-17-20

082520

Authorization to Negotiate

10/29/2024

409

Transmittal by Purchasing of a project scheduled for advertising

 

Location:

Address (if applicable): Project is bounded by Cullen Blvd. to the West and Clear Creek (Unit A100-00-00) to the to the East .

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds

$

$

$

$

1000 - General Fund

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$3,126,626.43

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Bonds

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$3,126,626.43

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: December 10, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Rashaun Jones, Project Manager, Capital Projects South; Maria Heinzmann, Senior Buyer, Harris County Purchasing

 

Attachments (if applicable):  Letter