Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): UPIN 22102MF2D601
Vendor/Entity Legal Name (if applicable): Scientech Engineers, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by Scientech Engineers, Inc., for Roadway - Reconstruction of Navigation Boulevard from Lockwood Drive to Mack Street 2021, UPIN 22102MF2D601, Precinct 2.
end
Background and Discussion:
The project is located in the City of Houston limits and is a joint participation project with Buffalo Bayou Partnership. Scientech Engineers, Inc. was awarded a contract to provide a Corridor Study to investigate the addition of a mixed use trail/bikeway along Navigation Boulevard from Lockwood Drive to Mack Street. Based on that agreement, Scientech has submitted the final study report on September 3rd, 2024.
Expected Impact:
The project will convert one existing travel lane in each direction on Navigation Boulevard to be able to provide for a wider center median which will provide for a new 12 feet dedicated bike and pedestrian route, thereby improving access to transit. It will include the addition of new six (6) feet sidewalks on both the north and south side of Navigation Boulevard, new Signal at Mac Farland and Navigation and partial augmentations to existing storm sewers and inlets to improve the drainage.
Alternative Options:
The County could elect to approve or choose to reject the study recommendations. However, if not approved, the design plans cannot be completed as recommended in the study.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
02/08/2022 |
22-0838 |
Authorization to Negotiate - Scientech Engineers, Inc. |
|
09/27/2022 |
22-5885 |
Award for Professional Engineering Services |
Location: Navigation Boulevard from Lockwood to Mack Street
Address (if applicable): N/A
Precinct(s): Precinct 2
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: October 29, 2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): N/A