Title: Request for approval of a change in contract with Environmental Allies, Inc., in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, with an addition in the amount of $3,552.00, Job No. 24/0084-1, UPIN 22102MF2G801, Precinct 2, MWBE Contracted Goal: 28.35%, MWBE Current Participation: 2.30%.

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: County Engineer

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0084, UPIN 22102MF2G801

Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.

 

MWBE Contracted Goal (if applicable): 28.35%

MWBE Current Participation (if applicable): 2.30%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Environmental Allies, Inc., in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, with an addition in the amount of $3,552.00, Job No. 24/0084-1, UPIN 22102MF2G801, Precinct 2, MWBE Contracted Goal: 28.35%, MWBE Current Participation: 2.30%.

end

 

Background and Discussion:

The project includes construction of intersection improvement for Vickery Street at Lauder Road.  The proposed improvements include alignment of the intersection of Vickery Street at Lauder Road, widening of the roads in all directions to construct turn lanes, full width concrete replacement along Vickery Street, and a traffic signal. Additional improvements include the construction of sidewalk, ADA ramps, and bus pads.

 

The removal of a streetlight was necessary to facilitate the re-alignment of the intersection within the project area.  The existing streetlight conflicted with the planned re-alignment and needed to be removed to ensure proper layout and alignment according to design specifications.  This change in contract will add additional amount of $3,552.00 with no additional calendar days.

 

Expected Impact:

Increase the total cost for the contract.

 

Alternative Options:

No action will result in substandard construction.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/14/2021

21-6787

Negotiate with IDS Engineering Group, Inc.

05/10/2022

22-2937

Execute an agreement with IDS Engineering Group, Inc.

09/13/2022

22-5535

Approval of a study report by IDS Engineering Group, Inc.

01/31/2023

23-0607

Approval to acquire 2 tracts

03/26/2024

24-1533

Negotiate with B2Z Engineering, LLC

05/07/2024

24-2712

Execute a SOLS

05/07/2024

24-2763

Contract Award to Environmental Allies, LLC

08/27/2024

24-5259

Execute an agreement with IDS Engineering Group, Inc.

 

Location:

Address (if applicable): Vickery Street

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund 3109

$

$3,552.00

$3,552.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$3,552.00

$3,552.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$3,552.00

$3,552.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/23/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, Chief of Engineering and Architectural Services, Harris County Engineering Department

 

Attachments (if applicable): County Auditor’s Form 1258B.