Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 24104MF3A401
Vendor/Entity Legal Name (if applicable): Harris County Municipal Utility District No. 540
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): Infrastructure (Design, Construction, Maintenance)
Request Summary (Agenda Caption):
title
Request for approval to execute an Interlocal Agreement with Harris County Municipal Utility District No. 540 in connection with Peek Road - from Stockdick School Road to Beckendorff Road - 2023, UPIN 24104MF3A401, Precinct 4.
end
Background and Discussion:
Based upon consultant's drainage report, it has been determined that approximately 1.88 acre-feet of detention capacity is needed to mitigate the additional storm water runoff due to the County's planned construction widening of Peek Road from Stockdick School Road to Beckendorff Road. This agreement is for the County's use of the District detention ponds to accommodate the County mitigation.
Expected Impact:
The related Peek Rd. project will address current and future traffic volumes, reduce delays, provide connectivity to schools and neighborhood destinations, improve safety for pedestrians and motorists, and improve roadway conditions. The use of the detention ponds subject to this ILA and the necessary drainage infrastructure will reduce potential flooding.
Alternative Options:
Alternative options include choosing not to widen Peek Rd and the accompanying drainage system.
County Strategic Plan Goal: 1. Make Harris County safer and more just.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan:
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
|
|
|
Location: Stockdick School Road to Beckendorff Road (Approximately 1.2 miles).
Address (if applicable): N/A
Precinct(s): Precinct 4
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Bonds Road |
$ |
$234,506.96 |
$234,506.96 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$234,506.96 |
$234,506.96 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$234,506.96 |
$234,506.96 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 11/12/2026
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Bashar Ahmed, Chief of Staff, Office of the County Engineer
Attachments (if applicable): ILA agreement and Exhibits