Legislation Details

File #: 26-0203    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/22/2025 In control: Commissioners Court
On agenda: 1/8/2026 Final action: 1/8/2026
Title: Request for approval of an amendment to an agreement with Agha Engineering LLC in the amount of $461,914.92 for Professional Engineering Services to provide improvements on Clay Road - Katy Hockley Rd to Katy Hockley Cutoff Rd - 2023, UPIN 24104MF3A201, Precinct 4, MWBE Contracted Goal: 19.60%, MWBE Current Participation: 100%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, Env. SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official:

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 24104MF3A201

Vendor/Entity Legal Name (if applicable): AGHA ENGINEERING LLC

 

MWBE Contracted Goal (if applicable): 19.60%

MWBE Current Participation (if applicable): 100%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with Agha Engineering LLC in the amount of $461,914.92 for Professional Engineering Services to provide improvements on Clay Road - Katy Hockley Rd to Katy Hockley Cutoff Rd - 2023, UPIN 24104MF3A201, Precinct 4, MWBE Contracted Goal: 19.60%, MWBE Current Participation: 100%.

end

 

Background and Discussion:

Harris County desires to amend the professional service agreement to extend the project limit around to 500 Ft east of Eula Morgan Rd due to continuous growth of the area, the new project limit is From 500 ft East of Eula Morgan Rd to 500 ft West of Katy Hockley Cut Off Road.

 

Expected Impact:

The project will upgrade and expand the capacity of the two-lane Asphalt roadway with 4 concrete lanes to handle the demands of the current and future traffic volumes. The improvement will alleviate congestion, reduce delays, and provide safe mobility for residents, pedestrians, and drivers in Northwest Katy; the project will provide safe crossings for students of Haskett Junior High School and Faldyn Elementary School.

Also upgrade the Road to concrete pavement will extend the pavement life and reduce the cost of road maintenance and rehabilitation.

 

 

Alternative Options:

If no action is taken, the benefits associated with the proposed improvement will not be achieved depriving the residents, businesses and road users of the advantages of these proposed improvements.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

12/10/2024

24-7706

Approval to execute an agreement with AGHA ENGINEERING LLC in the amount of $ 1,442,406.72. for Professional Engineering Services for carrying out a roadway improvement project on Clay Road - Katy Hockley Rd to Katy Hockley Cutoff Rd - 2023 , UPIN 24104MF3A201, Precinct 4

 

Location:

Address (if applicable): Clay Road - 500 Feet east of Eula Morgan to 500 Feet west of Katy Hockley Cutoff Rd., Katy, TX 77493

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3109

$

$461,914.92

$461,914.92

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$461,914.92

$461,914.92

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$461,914.92

$461,914.92

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 1/8/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Office of the County Enginee

 

Attachments (if applicable): Agreement Amendment