Legislation Details

File #: 25-5724    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/3/2025 In control: Commissioners Court
On agenda: 9/18/2025 Final action: 9/18/2025
Title: Request for approval of a change in contract with Wadecon, LLC, in connection with final construction of Lynwood Estates Subdivision Drainage Improvements - 2018, with a deduction in the amount of $258,952.35, Job No. 22/0183-4, UPIN 19104MF16H01, Precinct 3, MWBE Contracted Goal: 21%.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

 

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0183, UPIN 19104MF16H01

Vendor/Entity Legal Name (if applicable): Wadecon, LLC

 

MWBE Contracted Goal (if applicable): 21%

MWBE Current Participation (if applicable): 0.00%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Wadecon, LLC, in connection with final construction of Lynwood Estates Subdivision Drainage Improvements - 2018, with a deduction in the amount of $258,952.35, Job No. 22/0183-4, UPIN 19104MF16H01, Precinct 3, MWBE Contracted Goal: 21%.

end

 

Background and Discussion:

The Lynwood Estates Subdivision is located in Precinct 3, north of Beltway 8 and west of Hardy Service Rd. The project will improve the existing public drainage system in order to reduce ponding during the 2-year, 10-year, and 100-year storm events. The improvements include upsizing existing inlets, installing storm sewers and upsizing the system’s outfall to reinforced concrete boxes, and adding a detention pond to avoid adverse impacts to the receiving waterways.

 

The change in contract includes the following:

 

The line items are adjusted to reconcile underrun quantities on the project for completion of the proposed scope of work.

 

  • The increase of quantities on overrun line item numbers 4 and 6 for an addition in the amount of $1,321.10.
  • The decrease of quantities on underrun line item numbers 3, 5, 10, 12, 13, 14, 15, 16, 17, 18, 19, 20, 23, 33, 37, 38, 41, 47, 49, 53, 54, 55, 56, 57, 63, 64, 65, 66, 67, 68, 69, and 19A for a deduction in the amount of $260,273.45.

 

The above deductions result in a net deduction in the amount of ($258,952.35).

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Lynwood Estates subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be compensated for completing the scope of work.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/04/2023

218 (22-4395)

Contract Award – Wadecon LLC

08/08/2023

69 (23-4441)

Contract Amendment (22/0183-1) for additional funds and extension of project term

12/19/2023

59 (23-7006)

Contract Amendment (22/0183-2) for additional funds and extension of project term

04/23/2024

89 (21-2179)

Contract Amendment (22/0183-3) for additional funds and extension of project term

   05/08/2025

392 (25-2747)

Transmittal - Substantial Completion Certificate

 

Location: Lynwood Estates subdivision

Address (if applicable): N/A

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund                     

$

-$258,952.35

-$258,952.35

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$258,952.35

-$258,952.35

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$258,952.35

-$258,952.35

$

Grants – Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget:

Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request:

Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 09/18/2025

Anticipated Implementation Date (if different from Court date): N/A                     

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC) - FINAL