Title: Request for approval to execute an interlocal agreement with Metropolitan Transit Authority for design, construction and maintenance responsibilities in connection with Asphalt Rehabilitation - Memorial Drive between San Felipe and West of Chimney Rock - 2024, UPIN 25103MF3MT01, Precinct 3.
Attachments: 1. 25-6213-Partnership-UPIN 25103MF3MT01-Asphalt - Memorial Drive -METRO P3

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

 

Project ID (if applicable): UPIN 25103MF3MT01

Vendor/Entity Legal Name (if applicable): Metropolitan transit authority

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an interlocal agreement with Metropolitan Transit Authority for design, construction and maintenance responsibilities in connection with Asphalt Rehabilitation - Memorial Drive between San Felipe and West of Chimney Rock - 2024, UPIN 25103MF3MT01, Precinct 3.

end

 

Background and Discussion:

The Memorial Drive asphalt rehabilitation project is a joint project between multiple cities for a road segment that routes through their city limits.  The road segment requires maintenance to maintain the current service it provides to the local communities.

 

Expected Impact:

The intent of this agreement is to identify the responsibilities of Harris County and the Metropolitan Transit Authority.

 

Alternative Options:

The alternative is not to proceed with Metropolitan Transit Authority Agreement and Precinct will fund the entire project.

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Additional notes related to the Strategic Plan: n/a

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

 

Location: Memorial Drive between San Felipe and West of Chimney Rock

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 2022 Bond

$

$1,289,117

$$1,289,117

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$1,289,117

$1,289,117

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$$1,289,117

$1,289,117

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 10/16/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services,

Office of the County Engineer

 

Attachments (if applicable): Interlocal Agreement